Completed
Physical progress:
100%
Timeline:
Start Feb 18, 2025 (1 yr 8 mo ago) · Target/actual end Aug 25, 2025
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, ALIMODIAN CENTRAL ELEMENTARY SCHOOL, ALIMODIAN, ILOILO
Category:
GAA 2025 SSP
Implementing office:
DPWH Iloilo 4th DEO · Region VI
Contractor:
J'14 CONSTRUCTION AND SUPPLY · DPWH contractor code 40540
As listed: J'14 CONSTRUCTION & SUPPLY
Contract amount:
₱4,898,841.78 (₱4.9M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
30eb9b6cd55c…Feb 5, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 4TH DEO₱4,899,137.82

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GI0085Sep 9, 2025CONSTRUCTION OF SCHOOL BUILDING, SINAMAY ELEMENTARY SCHOOL, BARANGAY SINAMAY, ALIMODIAN, ILOILOOn-Going₱9.9M
25GI0087Sep 9, 2025CONSTRUCTION OF SCHOOL BUILDING, ALIMODIAN NATIONAL COMPREHENSIVE HIGH SCHOOL, ALIMODIAN, ILOILOOn-Going₱24.6M
25GI0053May 20, 2025CONSTRUCTION OF ROAD, BARANGAY QUINASPAN, ALIMODIAN, ILOILOCompleted₱9.8M
25GI0060May 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LAYLAYAN, ALIMODIAN, ILOILOOn-Going₱4.9M
25GI0061May 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BANCAL ELEMENTARY SCHOOL, ALIMODIAN, ILOILOCompleted₱4.9M
25GI0063May 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO KANANGHAN, BARANGAY BUGA, LEON, ILOILOCompleted₱4.9M
25GI0040Mar 25, 2025OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS - MANDURRIAO-SN MIGUEL- ALIMODIAN-MAASIN-CABATUAN RD - K0023 + 089 - K0023 + 860Completed₱34.6M
25GI0064Mar 11, 2025CONSTRUCTION OF AGANAN FLOOD CONTROL STRUCTURE, JARO-AGANAN RIVER, BARANGAY POBLACION, ALIMODIAN, ILOILOCompleted₱45.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.