Project 25GI0036
DPWH infrastructure contract
Contract ID:
25GI0036
Fingerprint:
1c8ea1523055b4…68c1eb88ce Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 25, 2025 (1 yr 7 mo ago) · Target/actual end Dec 26, 2025
Description:
CONSTRUCTION OF SIBALOM FLOOD CONTROL STRUCTURE, SIBALOM RIVER, BARANGAY NAGBANGI, LEON, ILOILO
Category:
GAA 2025 OO-2
Implementing office:
DPWH Iloilo 4th DEO · Region VI
Contractor:
J E G CONSTRUCTION FIRM CORPORATION · DPWH contractor code 36486
Contract amount:
₱29,129,998.95 (₱29.1M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9dc984fa552e… | Mar 12, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 4TH DEO | ₱29,130,000.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GI0068 | Sep 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, LEON, ILOILO | On-Going | ₱9.8M |
| 25GI0081 | Jul 11, 2025 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM | Completed | ₱2.6M |
| 25GI0059 | Jun 4, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BINOLBOG, LEON, ILOILO | Completed | ₱4.9M |
| 25GI0056 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TUOG, LEON, ILOILO | Completed | ₱4.9M |
| 25GI0057 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY IGCADIOS, LEON, ILOILO | On-Going | ₱4.9M |
| 25GI0058 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TACUYONG SUR, LEON, ILOILO | Completed | ₱4.9M |
| 25GI0039 | Mar 25, 2025 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - JCT BANCAL-LEON-ANTIQUE BDRY RD - K0042 + 435 - K0042 + 480 | Completed | ₱22.3M |
| 25GI0038 | Mar 14, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - JCT BANCAL-LEON-ANTIQUE BDRY RD - K0047 + 424 - K0047 + 630, K0047 + 788 - K0047 + 861 | Completed | ₱9.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.