Project 25GP0011

DPWH infrastructure contract
Contract ID:
25GP0011
Fingerprint:
d88f1ac83ea16d…0239e7a7f2 Verified
Status:
On-Going
Physical progress:
86.7%
Timeline:
Start Mar 26, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF RIVER CONTROL ALONG PANAY RIVER BASIN, BARANGAY SAN ROQUE, DUMALAG, CAPIZ
Category:
GAA 2025 OO-2
Implementing office:
DPWH Capiz 2nd DEO · Region VI
Contract amount:
₱96,229,311.63 (₱96.2M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GP0063Aug 15, 2025CONSTRUCTION OF SCHOOL BUILDING, DURAN ELEMENTARY SCHOOL, BRGY. DURAN, DUMALAG, CAPIZOn-Going₱5.0M
25GP0064Aug 15, 2025CONSTRUCTION OF SCHOOL BUILDING, CONCEPCION ELEMENTARY SCHOOL, BRGY. CONCEPCION, DUMALAG, CAPIZOn-Going₱5.0M
25GP0065Aug 15, 2025CONSTRUCTION OF SCHOOL BUILDING, DOLORES ELEMENTARY SCHOOL, BRGY. DOLORES, DUMALAG, CAPIZOn-Going₱5.0M
25GP0066Aug 15, 2025CONSTRUCTION OF SCHOOL BUILDING, CONSOLACION ELEMENTARY SCHOOL, BRGY. CONSOLACION, DUMALAG, CAPIZOn-Going₱5.0M
25GP0053Jun 6, 2025CONCRETING OF BRGY. SAN MARTIN FMR, BRGY. SAN MARTIN, DUMALAG, CAPIZOn-Going₱9.9M
25GP0015Jun 5, 2025CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, SITIO BAIDAN TO SITIO AGBALAGON, BARANGAY SAN MIGUEL, DUMALAG, CAPIZOn-Going₱19.8M
25GP0032Jun 5, 2025CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD LEADING TO NABAYE FALLS, BRGY. DURAN, DUMALAG, CAPIZOn-Going₱9.8M
25GP0007Mar 27, 2025CONSTRUCTION OF RIVER CONTROL ALONG PANAY RIVER BASIN, BARANGAY POBLACION ILAWOD TO BARANGAY SAN JOSE, DUMALAG, CAPIZOn-Going₱77.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.