Project 25GR0006
DPWH infrastructure contract
Contract ID:
25GR0006
Fingerprint:
9cd827588d9e15…c721f23f62 Verified
Status:
On-Going
Physical progress:
98.8%
Timeline:
Start Apr 10, 2025 (1 yr 7 mo ago)
Description:
ARC ROAD IN BARANGAY TOYUNGAN, CALINOG, ILOILO
Category:
Trust Funds 2024
Implementing office:
DPWH Iloilo 6th DEO · Region VI
Contractor:
TUPAS AGGREGATES CIVIL ENGINEERING CONSTRUCTION · DPWH contractor code 54254
Contract amount:
₱24,819,503.38 (₱24.8M)
Funding source:
Outside Infra - Trust Funds 2024
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GR0053 | Sep 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING IN RIZAL ST., POBLACION, BARANGAY ILAYA, CALINOG, ILOILO | On-Going | ₱9.7M |
| 25GG0112 | Jul 4, 2025 | ROAD WIDENING - ILOILO - CAPIZ RD (OLD ROUTE) - K0061+100 - K0061+430, K0061+445 - K0061+522 | On-Going | ₱12.2M |
| 25GG0008 | Jul 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY MALITBOG ILAYA, BINGAWAN, ILOILO | Completed | ₱3.0M |
| 25GG0009 | Jul 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY GAMA PEQUENO, CALINOG, ILOILO | Completed | ₱3.0M |
| 25GG0010 | Jul 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY TOYUNGAN, CALINOG, ILOILO | Completed | ₱3.3M |
| 24GR0003 | Apr 7, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG JALAUR RIVER(PACKAGE 3), CALINOG, ILOILO | On-Going | ₱140.2M |
| 25G00077 | Mar 24, 2025 | PREVENTIVE MAINTENANCE- ASPHALT OVERLAY OF PASSI- CALINOG RD K0054+1802- K0054+2872, K0058+065- K0060+192, K0060+1051- K0060+1112 | On-Going | ₱128.2M |
| 25GG0080 | Mar 4, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO - CAPIZ RD (OLD ROUTE) - K0059 + (-848) - K0060 + 538 | Completed | ₱88.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.