Project 25H00057
DPWH infrastructure contract
Contract ID:
25H00057
Fingerprint:
4002984050567f…059986a034 Verified
Status:
On-Going
Physical progress:
75.9%
Timeline:
Start Apr 11, 2025 (1 yr 7 mo ago)
Description:
OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG., CONST./ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONST. OF FLOOD CONTROL STRUCTURE ALONG PANOYPOY RIVER LEADING TO SANITARY LANDFILL AND CRUSHING PLANT
Category:
GAA 2025 OO-2
Implementing office:
DPWH Region VII · Region VII
Contractor:
VSP STRUCTURE VENTURES CORP. (FORMERLY: VIRLO CONSTRUCTION) · DPWH contractor code 5765
Contract amount:
₱96,410,977.69 (₱96.4M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 37abc59ebac9… | Feb 6, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ( REGIONAL OFFICE VI | ₱96,410,977.69 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24HN0235 | Aug 7, 2025 | CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), PUROK 5B, BARANGAY CANSAGA, CONSOLACION, CEBU | Terminated | ₱0 |
| 24H00180 | Jul 25, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, CONSOLACION-TAYUD-LILOAN RD - K0015 + 448 - K0015 +869 | On-Going | ₱26.9M |
| 25HN0125 | Jun 3, 2025 | SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, NORTH ROAD, BARANGAY CANSAGA, CONSOLACION, CEBU | On-Going | ₱1.9M |
| 25HN0133 | Jun 3, 2025 | SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CANSAGA RIVER, BARANGAY TILHAONG, CONSOLACION, CEBU | Completed | ₱48.5M |
| 25HN0134 | Jun 3, 2025 | SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF NANGKA - TUGBONGAN ROAD WITH SLOPE PROTECTION SYSTEM, CONSOLACION, CEBU | On-Going | ₱48.5M |
| 25HN0138 | Jun 3, 2025 | CP: SPECIAL ROAD FUND - MVUC AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES ALONG MACTAN CIRCUMFERENTIAL ROAD - K0028+000 - K0030+365, CORDOVA, CEBU AND CEBU NOTH HAGNAYA WHARF RD - K0011+657 - K0014+505, CONSOLACION, CEBU | Completed | ₱48.0M |
| 25HN0148 | Jun 3, 2025 | SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF NANGKA-TUGBUNGGAN ROADS, CONSOLACION, CEBU (PACKAGE I) | On-Going | ₱97.0M |
| 25HN0152 | Jun 3, 2025 | SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY TILHAONG, CONSOLACION, CEBU | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.