Project 25HA0039
DPWH infrastructure contract
Contract ID:
25HA0039
Fingerprint:
2757c738cf72bf…0ea34b02ba Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 10, 2025 (1 yr 9 mo ago) · Target/actual end Jun 7, 2025
Description:
INSTALLATION/ APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGTHING) ALONG THE PRESIDENT CARLOS P. GACIA CIRCUMFERENTIAL RD - K0010+434 - K0010+676, K0011+000 - K0013+500, K0014+000 - K0014+400, K0014+740 - K0016+680, K0017+000 - K0018+000, K0018+450 -
Category:
Roads
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
N.N. YU CONSTRUCTION, INC. · DPWH contractor code 10470
As listed: N.N. YU CONSTRUCTION, INC. (FORMERLY: YU CONSTRUCTION)
Contract amount:
₱38,225,000.00 (₱38.2M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 953d58dbc650… | Jan 27, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BOHOL 1ST ED | ₱38,225,000.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HA0123 | Feb 13, 2026 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (GOVERNMENT CENTER), MALAYO SUR, CORTES, BOHOL | On-Going | ₱99.0M |
| 24HA0160 | May 15, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT BARANGAY MALAYO NORTE TO BARANGAY LORETO ALONG ABATAN RIVER, CORTES, BOHOL | On-Going | ₱96.0M |
| 25HA0047 | May 15, 2025 | CONSTRUCTION OF ROAD, MALAYO SUR, CORTES, BOHOL | Completed | ₱9.8M |
| 25HA0095 | May 15, 2025 | RIHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - JCT (TNR) CORTES-BALILIHAN-CATIGBIAN-MACAAS RD - K0010+299 - K0010+323, K0014+798 - K0014 + 855, K0015 + 028 - K0015 + 050, K0015 + 291 - K0015 + 384, K00 | Completed | ₱4.5M |
| 25H00035 | Apr 11, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (PHASE II), VIGA, ANTEQUERA, BOHOL | On-Going | ₱101.2M |
| 25HA0051 | Mar 27, 2025 | CONSTRUCTION OF FATIMA BRIDGE, BARANGAY FATIMA, CORTES, BOHOL | Completed | ₱11.8M |
| 25HA0027 | Feb 10, 2025 | REHABILITATION OF DPWH AREA EQUIPMENT SERVICE BUILDING, DE LA PAZ, CORTES, BOHOL | Completed | ₱19.6M |
| 24HA0021 | May 28, 2024 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - JCT (TNR) CORTES-BALILIHAN-CATIGBIAN-MACAAS RD - K0012 + 521 - K0012 + 710, K0045 + 655 - K00455 + 666, K0045 + 745 - K0045 + 752 | Completed | ₱3.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.