Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25HK0022

DPWH infrastructure contract
Contract ID:
25HK0022
Fingerprint:
7bcb54a978378b…d10d467b7f Verified
Status:
On-Going
Physical progress:
50.0%
Timeline:
Start Feb 20, 2025 (1 yr 8 mo ago)
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES,INDUSTRIES AND ECONOMIC ZONES(ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL-IT) E.J BLANCO ROAD CONNECTING TO THE DUMAGUETE
Category:
GAA 2025 CP
Implementing office:
DPWH Negros Oriental 2nd DEO · Negros Island Region
Contractor:
Contract amount:
₱19,400,046.16 (₱19.4M)
Funding source:
Regular Infra - GAA 2025 CP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25HK0086May 23, 2025CONSTRUCTION OF THREE(3) STOREY FIFTEEN (15) CLASSROOMS SCHOOL BUILDING AT BATINGUEL ELEMENTARY SCHOOL, DUMAGUETE CITY, NEGROS ORIENTALOn-Going₱46.2M
25HK0092May 23, 2025CONSTRUCTION/REHABILITATION OF RAINWATER COLLECTOR SYSTEM OF THE FOLLOWING SITES:1.)PAMPLONA CENTRAL ELEMENTARY SCHOOL,BARANGAY POBLACION,PAMPLONA,NEGROS ORIENTAL 2.)TACLOBO HIGH SCHOOL,BARANGAY TACLOBO,DUMAGUETE CITY,NEGROS ORIENTAL 3.)HUNOP ELEMENTARYCompleted₱2.6M
25HK0059Mar 28, 2025ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CALINDAGAN AND BARANGOn-Going₱101.1M
25HK0053Mar 21, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE-PRIMARY ROADS ALONG DUMAGUETE SOUTH RD-K0001+270-K0002+470Completed₱34.3M
25HK0075Mar 21, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG DUMAGUETE SOUTH ROAD K0002+470-K0003+770On-Going₱48.0M
25HK0066Feb 21, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-METRO DUMAGUETE DIVERSION ROAD, NEGROS ORIENTALOn-Going₱19.9M
25HK0033Feb 20, 2025ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS:CONSTRUCTION OF SLOPE PROTECTION STRUCTURE,CANDAU-AY-BATINGUEL CIS,DUMAGUETE CITYOn-Going₱14.5M
25HK0006Feb 19, 2025BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY BANTAYAN, DUMAGUETE CITY, NEGROS ORIENTALCompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.