Project 25HK0064
DPWH infrastructure contract
Contract ID:
25HK0064
Fingerprint:
6fcf37e35bcad5…c9cce26649 Verified
Status:
On-Going
Physical progress:
44.8%
Timeline:
Start Mar 28, 2025 (1 yr 7 mo ago)
Description:
ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABANKALAN)-K0005+220 - K0006+000
Category:
GAA 2025 OO-1
Implementing office:
DPWH Negros Oriental 2nd DEO · Negros Island Region
Contractor:
RICHFIELD BUILDERS, INC. (FORMERLY: RICHFIELD BUILDERS) · DPWH contractor code 24525
Contract amount:
₱48,740,572.50 (₱48.7M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| c6bd0170d7d4… | Mar 20, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NEGROS ORIENTAL 2N | ₱48,740,572.50 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HK0082 | May 23, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF REVETMENT STRUCTURE ALONG OCOY RIVER, BRGY. CALABNUGAN, SIBULAN, NEGROS ORIENTAL | Completed | ₱146.3M |
| 25HK0042 | Mar 28, 2025 | ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DUMAGUETE NORTH ROAD(DUMAGUETE-JCT-BAIS-KABANKALAN)-K0002+863-K0003+480,NEGROS ORIENTAL | On-Going | ₱39.8M |
| 25HK0062 | Mar 28, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABANKALAN) - K0004+000 - K0004+940 | On-Going | ₱58.8M |
| 25HK0037 | Mar 20, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - TINAPAYAN-CAMBAJAO ROAD LEADING TO PUNCAK, TANAWAN, BALUGO, SIBULAN, NEGROS ORIENTAL | On-Going | ₱9.8M |
| 25HK0073 | Feb 21, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANICA RIVER, DUMAGUETE CITY, N | Completed | ₱102.0M |
| 25HK0048 | Feb 20, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM -ROAD WIDENING - PRIMARY ROADS-DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABANKALAN)- K0003+491-K0004+000 | On-Going | ₱32.1M |
| 25HK0012 | Feb 19, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF SEAWALL,BARANGAY AGAN-AN, SIBULAN, NEGROS ORIENTAL | On-Going | ₱9.9M |
| 24HK0114 | May 29, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF LOOC SHORE PROTECTION, LOOC, SIBULAN | Completed | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.