Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25IA0128

DPWH infrastructure contract
Contract ID:
25IA0128
Fingerprint:
b1129998c5d2e5…6114d6d00e Verified
Status:
On-Going
Physical progress:
89.0%
Timeline:
Start Mar 25, 2025 (1 yr 7 mo ago)
Description:
CONCRETING OF BRGY. BOOL-WEST FMR, BRGY. BOOL-WEST, CULABA, BILIRAN
Category:
GAA 2025 DA FMR
Implementing office:
DPWH Biliran DEO · Region VIII
Contractor:
RMA BUILDERS & SUPPLIES CORPORATION · DPWH contractor code 53055
Contract amount:
₱14,918,500.00 (₱14.9M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26IA0005May 13, 2026NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1061+078 - K1062+400On-Going₱47.2M
25IA0145Jun 30, 2025CONSTRUCTION OF ROAD, BARANGAY BINONGTOAN, CULABA, BILIRANOn-Going₱14.8M
25IA0150Jun 30, 2025CONSTRUCTION OF SEAWALL, BARANGAY SAN ROQUE, CULABA, BILIRANCompleted₱14.7M
25I00128Apr 16, 2025ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD. - K1071+895 - K1072+180On-Going₱144.6M
25IA0049Mar 10, 2025NETWORK DEVELOPMENT - CONSTRUCTION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1066+170 - K1067+900On-Going₱36.2M
25IA0122Mar 7, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BACOLOD, CULABA, BILIRANCompleted₱4.9M
25IA0013Mar 4, 2025CONSTRUCTION OF BOOL FLOOD CONTROL STRUCTURE ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE V, CULABA, BILIRANCompleted₱49.1M
25IA0071Mar 4, 2025CONSTRUCTION OF BOOL WEST FLOOD CONTROL STRUCTURE, PHASE I, CULABA, BILIRANCompleted₱29.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.