Project 25IA0128
DPWH infrastructure contract
Contract ID:
25IA0128
Fingerprint:
b1129998c5d2e5…6114d6d00e Verified
Status:
On-Going
Physical progress:
89.0%
Timeline:
Start Mar 25, 2025 (1 yr 7 mo ago)
Description:
CONCRETING OF BRGY. BOOL-WEST FMR, BRGY. BOOL-WEST, CULABA, BILIRAN
Category:
GAA 2025 DA FMR
Implementing office:
DPWH Biliran DEO · Region VIII
Contractor:
RMA BUILDERS & SUPPLIES CORPORATION · DPWH contractor code 53055
Contract amount:
₱14,918,500.00 (₱14.9M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26IA0005 | May 13, 2026 | NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1061+078 - K1062+400 | On-Going | ₱47.2M |
| 25IA0145 | Jun 30, 2025 | CONSTRUCTION OF ROAD, BARANGAY BINONGTOAN, CULABA, BILIRAN | On-Going | ₱14.8M |
| 25IA0150 | Jun 30, 2025 | CONSTRUCTION OF SEAWALL, BARANGAY SAN ROQUE, CULABA, BILIRAN | Completed | ₱14.7M |
| 25I00128 | Apr 16, 2025 | ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD. - K1071+895 - K1072+180 | On-Going | ₱144.6M |
| 25IA0049 | Mar 10, 2025 | NETWORK DEVELOPMENT - CONSTRUCTION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1066+170 - K1067+900 | On-Going | ₱36.2M |
| 25IA0122 | Mar 7, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BACOLOD, CULABA, BILIRAN | Completed | ₱4.9M |
| 25IA0013 | Mar 4, 2025 | CONSTRUCTION OF BOOL FLOOD CONTROL STRUCTURE ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE V, CULABA, BILIRAN | Completed | ₱49.1M |
| 25IA0071 | Mar 4, 2025 | CONSTRUCTION OF BOOL WEST FLOOD CONTROL STRUCTURE, PHASE I, CULABA, BILIRAN | Completed | ₱29.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.