Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25IB0126

DPWH infrastructure contract
Contract ID:
25IB0126
Fingerprint:
23cea96a3e43a3…231e8cf6d5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 14, 2025 (1 yr 2 mo ago) · Target/actual end Sep 30, 2025
Description:
CONCRETING OF BRGY. GAP-ANG FMR, BRGY. GAP-ANG, DOLORES, EASTERN SAMAR
Category:
GAA 2025 DA FMR
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
JEAZ CONSTRUCTION · DPWH contractor code 59301
Contract amount:
₱4,969,989.25 (₱5.0M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IB0188Jan 22, 2026CONSTRUCTION OF CLASSROOMS, AROGANGA ELEMENTARY SCHOOL, BARANGAY AROGANGA, DOLORES, EASTERN SAMAROn-Going₱8.6M
25IB0208Jan 22, 2026REPAIR/ REHABILITATION OF CLASSROOMS, CAGLAO-AN ELEMENTARY SCHOOL, DOLORES, EASTERN SAMARCompleted₱4.5M
25IB0180Dec 16, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BRGY. 2 - BRGY. MALAINTOS ALONG DOLORES RIVER, DOLORES, EASTERN SAMAROn-Going₱95.4M
25IB0161Nov 17, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT BRGY. SAN VICENTE ALONG DOLORES RIVER DOLORES, EASTERN SAMAROn-Going₱48.0M
25IB0163Nov 13, 2025REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG DOLORES RIVER PROTECTING BARANGAY ROAD, STO. NIÑO, DOLORES, EASTERN SAMAROn-Going₱48.0M
25IB0166Nov 13, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BRGY. SAN ISIDRO, DOLORES, EASTERN SAMAROn-Going₱48.0M
25IB0118Oct 9, 2025CONSTRUCTION OF ROAD ALONG CAROLINA - DOLORES - MASLOG, EASTERN SAMAROn-Going₱29.3M
25IB0121Aug 26, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT BRGY. DEL PILAR ALONG DOLORES RIVER, DOLORES, EASTERN SAMAROn-Going₱48.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.