Project 25IB0131
DPWH infrastructure contract
Contract ID:
25IB0131
Fingerprint:
5538ffecc6799f…446dc25a5a Verified
Status:
On-Going
Physical progress:
97.8%
Timeline:
Start Aug 14, 2025 (1 yr 2 mo ago)
Description:
CONCRETING OF BRGY. GARAWON TO BRGY. CACATMONAN FMR, BRGY. GARAWON AND BRGY. CACATMONAN, HERNANI, EASTERN SAMAR
Category:
GAA 2025 DA FMR
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
AICON INDUSTRIES · DPWH contractor code 48423
Contract amount:
₱14,919,984.76 (₱14.9M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IB0077 | Jun 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CANCILEDES, HERNANI, EASTERN SAMAR | On-Going | ₱4.9M |
| 25I00120 | Apr 10, 2025 | SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF ROAD, BARANGAY PADANG - BARANGAY CANCILEDES, HERNANI, EASTERN SAMAR | On-Going | ₱33.7M |
| 24IB0112 | Jun 11, 2024 | CONSTRUCTION OF UNIVERSITY BUILDING, EASTERN SAMAR STATE UNIVERSITY, MUNICIPALITY OF GUIUAN, EASTERN SAMAR | Completed | ₱14.8M |
| 24IB0049 | Mar 18, 2024 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE SECONDARY ROADS, BORONGAN-GUIUAN RD, K1001+317 - K1001+417 | On-Going | ₱8.8M |
| 24IB0035 | Mar 11, 2024 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE SECONDARY ROADS, BORONGAN-GUIUAN RD K0988+845-K0988+910 | Completed | ₱5.9M |
| 24IB0037 | Mar 11, 2024 | CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS, BORONGAN - GUIUAN RD, K1000+455 - K1000+815 | Completed | ₱4.9M |
| 23IB0136 | Aug 17, 2023 | CONSTRUCTION OF 1STY2CL, PADANG ELEMENTARY SCHOOL, HERNANI, EASTERN SAMAR | Completed | ₱5.7M |
| 23I00084 | Jul 12, 2023 | SIPAG - FLOOD CONTROL MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY POBLACION, HERNANI, EASTERN SAMAR | Completed | ₱24.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.