Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25IB0135

DPWH infrastructure contract
Contract ID:
25IB0135
Fingerprint:
ede308ca2ca274…69b39ba846 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 14, 2025 (1 yr 2 mo ago) · Target/actual end Nov 7, 2025
Description:
CONCRETING OF BRGY. CAISAWAN TO SITIO JUMALAG FMR, BRGY. CAISAWAN, BALANGKAYAN, EASTERN SAMAR
Category:
GAA 2025 DA FMR
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
AICON INDUSTRIES · DPWH contractor code 48423
Contract amount:
₱14,919,992.60 (₱14.9M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26IB0070Sep 14, 2026CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS FACILITIES. CONSTRUCTION OF ROAD, BONAVENTURA STREET TO MONTES STREET, BALANGKAYAN, EOn-Going₱4.7M
26IB0019Aug 13, 2026CONSTRUCTION (COMPLETION) OF GYMNASIUM WITH FACILITIES, POBLACION BALANGKAYAN, EASTERN SAMAROn-Going₱9.4M
26IB0075Jul 14, 2026NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS BASEY-MAYDOLONG ROAD, BARANGAY DEL PILAR, MAYDOLONG, EASTERN SAMAR (STA. 22+993 - STA. 24+073) BARANGAY DEL PILAR, MAYDOLONG, EASTERN SAMAR (STA. 22+993 - STA. 24+073)On-Going₱123.8M
25IB0186Jan 22, 2026CONSTRUCTION OF CLASSROOMS, STA. FE NATIONAL HIGH SCHOOL, BRGY. STA. FE, BORONGAN CITY, EASTERN SAMAROn-Going₱8.5M
25IB0189Jan 22, 2026CONSTRUCTION OF CLASSROOMS, BALANGKAYAN ELEMENTARY SCHOOL, BALANGKAYAN, EASTERN SAMAROn-Going₱8.6M
25IB0190Jan 22, 2026CONSTRUCTION OF CLASSROOMS, GEN. MACARTHUR CENTRAL ELEMENTARY SCHOOL, GENERAL MACARTHUR, EASTERN SAMAROn-Going₱8.6M
25IB0196Jan 22, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDING (HALL) BARANGAY SUROK, BORONGAN CITY, EASTERN SAMAROn-Going₱4.8M
25IB0197Jan 22, 2026REPAIR/ REHABILITATION OF CLASSROOMS, EUGENIO A. ABUNDA SR. ELEMENTARY SCHOOL, CITY OF BORONGAN, EASTERN SAMARCompleted₱2.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.