Project 25IB0171
DPWH infrastructure contract
Contract ID:
25IB0171
Fingerprint:
4eeec46644fbba…b5cfd2968a Verified
Status:
On-Going
Physical progress:
97.0%
Timeline:
Start Nov 12, 2025 (11 mos ago)
Description:
CONSTRUCTION OF ROAD, BRGY. BUA-BUA - BRGY. ALOG - BRGY. MATARINAO, SALCEDO, EASTERN SAMAR
Category:
GAA 2025 SSP
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
HANZGRACE CONSTRUCTION AND TRADING CORP. · DPWH contractor code 54922
Contract amount:
₱47,774,999.99 (₱47.8M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IB0201 | Jan 22, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, SALCEDO NATIONAL HIGH SCHOOL, SALCEDO, EASTERN SAMAR | Completed | ₱14.1M |
| 25IB0068 | Aug 26, 2025 | CONSTRUCTION OF MULTI- PURPOSE BUILDING (SCHOOL BUILDING), SALCEDO NATIONAL VOCATIONAL HIGHSCHOOL, BRGY. NAPARAAN, SALCEDO, EASTERN SAMAR | Completed | ₱5.9M |
| 25IB0139 | Aug 26, 2025 | CONSTRUCTION OF POLICE STATION IN MUNICIPALITY OF SALCEDO, EASTERN SAMAR | On-Going | ₱10.4M |
| 25IB0134 | Aug 14, 2025 | CONCRETING OF BRGY. ABEJAO TO BRGY. SEGUINON FMR, BRGY. ABEJAO AND BRGY. SEGUINON, SALCEDO, EASTERN SAMAR | On-Going | ₱5.0M |
| 25IB0108 | Jul 14, 2025 | CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM 1. MUNICIPAL BUILDING, BARANGAY 03, SALCEDO, EASTERN SAMAR 2. EVACUATION CENTER, BRGY. NAPARAAN, SALCEDO, EASTERN SAMAR 3. MUNICIPAL BUILDING, BRGY. 4, JIPAPAD, EA | Completed | ₱2.6M |
| 25IB0062 | Jun 3, 2025 | CONSTRUCTION OF BRIDGE, BRGY. MALBOG, SALCEDO, EASTERN SAMAR | On-Going | ₱4.8M |
| 25IB0078 | Jun 3, 2025 | CONSTRUCTION OF ACADEMIC BUILDING, ESSU, SALCEDO, EASTERN SAMAR | Completed | ₱14.8M |
| 25IB0067 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS, BORONGAN - GUIUAN RD - K1026+182 - K1026+192 | Completed | ₱2.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.