Project 25IF0079
DPWH infrastructure contract
Contract ID:
25IF0079
Fingerprint:
bc30e5c35fe1fe…fa2894979a Verified
Status:
On-Going
Physical progress:
95.9%
Timeline:
Start Jun 16, 2025 (1 yr 4 mo ago)
Description:
CONCRETING OF BRGY. SAN FRANCISCO TO BRGY. BANTIGUE FMR, BRGY. SAN FRANCISCO AND BRGY. BANTIGUE, ISABEL, LEYTE
Category:
GAA 2025 DA FMR
Implementing office:
DPWH Leyte 4th DEO · Region VIII
Contractor:
L.N.R. CONSTRUCTION · DPWH contractor code 14148
Contract amount:
₱19,898,951.89 (₱19.9M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IF0102 | Dec 15, 2025 | CONSTRUCTION OF ROAD, PUTING BATO - CANGAG - CAN-ANDAN RD, ISABEL, LEYTE | On-Going | ₱49.0M |
| 25IF0067 | Mar 26, 2025 | ROAD WIDENING - SECONDARY ROADS - PALOMPON-ISABEL-MERIDA-ORMOC RD - K1086+722-K1088+200 | On-Going | ₱105.6M |
| 25IF0002 | Mar 19, 2025 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGE PAVED ROADS - TERTIARY ROADS - MERIDA - LUNDAG - PUTING BATO - CONSOLACION - ISABEL RD - K1109+577-K1109+662, K1114+410-K1114+770, K1117+710-K1117+880, K1122+000-K1122+117, K1123+043-K1123+118 | On-Going | ₱31.0M |
| 25IF0063 | Mar 18, 2025 | CONSTRUCTION OF CONCRETE ROAD, GAWAD KALINGA, BARANGAY STA. CRUZ, ISABEL, LEYTE | Completed | ₱14.6M |
| 25IF0027 | Feb 18, 2025 | CONSTRUCTION OF CONCRETE ROAD - BARANGAY ANISLAG, ISABEL, LEYTE | On-Going | ₱19.2M |
| 24IF0080 | Jun 7, 2024 | CONSTRUCTION OF 1-UNIT 3-CLASSROOM SCHOOL BUILDING, APALE ELEMENTARY SCHOOL IN ISABEL, LEYTE | Completed | ₱8.9M |
| 24IF0072 | May 27, 2024 | CONSTRUCTION OF 1-STOREY 3-CLASSROOM SCHOOL BUILDING IN SAN FRANCISCO ELEMENTARY SCHOOL, BARANGAY SAN FRANCISCO, ISABEL, LEYTE | Completed | ₱7.5M |
| 24IF0074 | May 27, 2024 | CONSTRUCTION OF 1-STOREY 3-CLASSROOM SCHOOL BUILDING IN ANISLAG ELEMENTARY SCHOOL, BARANGAY ANISLAG, ISABEL, LEYTE | Completed | ₱7.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.