Project 25IF0098
DPWH infrastructure contract
Contract ID:
25IF0098
Fingerprint:
b31011aae6df16…75db8005b4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 2, 2025 (1 yr 2 mo ago) · Target/actual end Feb 28, 2026
Description:
CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM, KANANGA, LEYTE
Category:
GAA 2025 SSP
Implementing office:
DPWH Leyte 4th DEO · Region VIII
Contractor:
RJIR ENTERPRISES CORPORATION · DPWH contractor code 34843
Contract amount:
₱29,685,149.73 (₱29.7M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IF0048 | Jul 1, 2025 | ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - LIBUNGAO - MATAG-OB - PALOMPON RD - K0991+460 - K0992+000 | Completed | ₱43.0M |
| 25IF0016 | Mar 26, 2025 | CONSTRUCTION OF CANAWAGAN FLOOD CONTROL (UPSTREAM) POBLACION AND BRGY. NATUBGAN, KANANGA, LEYTE | On-Going | ₱96.4M |
| 25IF0012 | Mar 25, 2025 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - LIBUNGAO - MATAG-OB - PALOMPON RD - K0995+580 - K0996+128.1, K0996+172 - K0996+673.5, K0996+700 - K0996+980, K0998+518 - K0998+993 | On-Going | ₱33.4M |
| 25IF0071 | Mar 20, 2025 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - BAO BRIDGE (B00184LT) ALONG PALO-CARIGARA-ORMOC ROAD | Completed | ₱14.5M |
| 25IF0061 | Mar 18, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - PALO - CARIGARA - ORMOC RD - K0984+(-361.4)-K0984+(-264), K0984+088 - K0984+238, K0985+063 - K0985+160, K0985+774 - K0985+800, K0989+645 - K0989+705, K0990+ | On-Going | ₱19.5M |
| 25IF0054 | Mar 3, 2025 | ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - PALO - CARIGARA - ORMOC RD - K0988+065 - K0989+068 | Completed | ₱66.3M |
| 25IF0009 | Feb 26, 2025 | CONSTRUCTION OF SANTO NIÑO FLOOD CONTROL STRUCTURE, BARANGAY SANTO NIÑO, KANANGA, LEYTE | On-Going | ₱96.0M |
| 25IF0023 | Feb 26, 2025 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING, PAVEMENT MARKINGS) ALONG PALO-CARIGARA-ORMOC RD - K0989+000 - K0991+345.11 | Completed | ₱19.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.