Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25IG0040

DPWH infrastructure contract
Contract ID:
25IG0040
Fingerprint:
db9e60e3c08960…74c9293b8b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 20, 2025 (1 yr 5 mo ago) · Target/actual end Nov 15, 2025
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TABUNOK, BATO, LEYTE
Category:
GAA 2025 SSP
Implementing office:
DPWH Leyte 5th DEO · Region VIII
Contractor:
JSONS BUILDERS · DPWH contractor code 45156
Contract amount:
₱4,944,000.00 (₱4.9M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1b20bea4a05d…Mar 18, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 5TH ED₱4,944,000.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26IG0019Jul 27, 2026CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BATO BY-PASS ROAD, STA. 2+233 - 2+513, BARANGAY TABUNOK, LEYTEOn-Going₱33.0M
25IG0010Jun 3, 2025CONSTRUCTION OF ROAD, SITIO KAMANGGAHAN, BARANGAY BAGO, BATO, LEYTECompleted₱4.9M
25IG0065Jun 3, 2025NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BATO-BONTOC RD - K1117 + 879 - K1120+000On-Going₱77.2M
25IG0055May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY ANAHAWAN, BATO, LEYTECompleted₱3.0M
25IG0063May 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY KALANGGAMAN, BATO, LEYTECompleted₱4.9M
25IG0016Mar 27, 2025NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BATO BY-PASS ROAD, LEYTECompleted₱19.6M
25IG0014Mar 11, 2025CONSTRUCTION OF ROAD, BARANGAY TAGAYTAY, BATO, LEYTECompleted₱4.9M
25IG0022Mar 11, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY RIVILLA, BATO, LEYTECompleted₱2.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.