Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25II0037

DPWH infrastructure contract
Contract ID:
25II0037
Fingerprint:
ab6b18125d9c40…f2f8d22a71 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 7, 2025 (1 yr 8 mo ago) · Target/actual end Aug 24, 2025
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 1, BRGY. BANTAYAN, SAN ROQUE, NORTHERN SAMAR
Category:
GAA 2025 SSP
Implementing office:
Contractor:
J.D. PARTUZA CONSTRUCTION · DPWH contractor code 39161
Contract amount:
₱9,887,911.31 (₱9.9M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
ed48bc8185b8…Jan 15, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTHERN SAMAR 2ND₱9,887,911.30

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26II0035Jul 24, 2026OFF-CARRIAGEWAY IMPROVEMENT, SECONDARY ROADS, CATARMAN-LAOANG RD, K0765+600 - K0765+710, NORTHERN SAMAR, 2ND DISTRICTOn-Going₱3.4M
25II0062Sep 15, 2025CONSTRUCTION OF SCHOOL BUILDING, BANTAYAN ELEMENTARY SCHOOL, SAN ROQUE, NORTHERN SAMARCompleted₱9.9M
25II0055Jul 7, 2025CONSTRUCTION/REHAB. OF RAINWATER COLLECTORS SYSTEM (RWCS) IN PUBLIC FACILITIES AT BALNASAN ES, BANTAYAN ES, DALE ES, LAOANGAN ES, MALOBAGO ES, MALOBAGO-PAGSANG-AN NHS, PAGSANG-AN ES, ALL OF SAN ROQUE, N. SAMAR & CABABTOAN ES, CAMPARANGA ES,CANJUMADAL ES,Completed₱2.6M
25II0054Jun 16, 2025CONCRETING OF SITIO CAMAMBANAN TO SITIO GUINBANDERAHAN, BRGY. BANTAYAN FMR, SAN ROQUE, NORTHERN SAMARCompleted₱14.9M
25II0046Jun 9, 2025CONSTRUCTION OF BRGY. DALY-BRGY. BALUD ROAD, SAN ROQUE, NORTHERN SAMARCompleted₱29.1M
25II0029Apr 7, 2025REHAB. OF ROAD, DOÑA ANECITA-DALE ROAD, NORTHERN SAMAR, SECOND DISTRICT, NORTHERN SAMARCompleted₱57.9M
25II0002Mar 28, 2025PREVENTIVE MAINTENANCE, TERTIARY ROADS, SN ROQUE-CABTOAN OLD RD., K0772+740-K0772+755; K0772+938-K0772+942.50; K0773+042-K0773+051; K0773+095-K0773+299; K0776+150-K0776+177, SN ROQUE & PAMBUJAN, NORTHERN SAMARCompleted₱2.9M
25II0019Mar 7, 2025REHAB. OF BANTAYAN FLOOD CONTROL STRUCTURE, BANTAYAN RIVER BASIN, SAN ROQUE, NORTHERN SAMARCompleted₱48.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.