Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25II0042

DPWH infrastructure contract
Contract ID:
25II0042
Fingerprint:
31d62a6dafbd7b…322e890cc4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 30, 2025 (1 yr 9 mo ago) · Target/actual end Apr 10, 2026
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. ALANG-ALANG, LAPINIG, NORTHERN SAMAR
Category:
GAA 2025 SSP
Implementing office:
Contractor:
CDU CONSTRUCTION · DPWH contractor code 13915
Contract amount:
₱9,884,377.39 (₱9.9M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
9ad63ce13dd7…Jan 15, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTHERN SAMAR 2ND₱9,884,377.39

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26II0013Jul 29, 2026REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE, SECONDARY ROADS, SN POLICARPO-ARTECHE-LAPINIG RD, K0858+300 - K0858+550, K0860+500 - K0860+700, NORTHERN SAMAR, 2ND DISTRICTOn-Going₱79.7M
25I00034Mar 7, 2025ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - SN POLICARPO - ARTECHE - LAPINIG RD - K0863+750 - K0864+000On-Going₱192.9M
24II0087Sep 4, 2024CONSTRUCTION OF ONE (1)-STOREY TWO (2)-CLASSROOM SCHOOL BUILDING IN ALANG-ALANG ELEMENTARY SCHOOL, BRGY. ALANG-ALANG, LAPINIG, NORTHERN SAMARCompleted₱5.9M
24II0068Jun 10, 2024CONSTRUCTION OF EVACUATION CENTER, BRGY. PALANAS, LAPINIG, NORTHERN SAMARCompleted₱9.6M
24II0005Apr 25, 2024REHAB./RECONSTRUCTIOIN/UPGRADING OF DAMAGED PAVED ROADS, SECONDARY ROADS, SN POLICARPO-ARTECHE-LAPINIG RD., K0853+722-K0853+825, 2ND DISTRICT, NORTHERN SAMARCompleted₱4.7M
24II0070Apr 25, 2024CONCRETING OF ROAD IN BRGY. IMELDA-CAN OMANIO-PIO DEL PILAR (5 KMS), LAPINIG, NORTHER SAMARCompleted₱19.8M
24II0006Feb 7, 2024REHAB./RECONSTRUCTION OF ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SECONDARY ROADS, SN POLICARPO-ARTECHE-LAPINIG RD. K0852+790-K0852+940; K0853+526-K0853+613; K0854+735-K0854+850; K0857+470-K0857+630; K0858+675-K0858+928, 2ND DISTRICT, NORTHERN SAMARCompleted₱95.8M
24II0015Feb 7, 2024ROAD WIDENING, SECONDARY ROADS, SN POLICARPO-ARTECHE-LAPINIG RD., K0856+000-K0857+000, 2ND DISTRICT NORTHERN SAMARCompleted₱57.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.