Project 25IM0077
DPWH infrastructure contract
Contract ID:
25IM0077
Fingerprint:
e66cf57e2d3037…01af86266b Verified
Status:
On-Going
Physical progress:
80%
Timeline:
Start May 28, 2025 (1 yr 5 mo ago)
Description:
CONCRETING OF BRGY. STA. ELENA, TACLOBAN CITY TO BRGY. BAGONG SILANG, BABATNGON FMR, TACLOBAN CITY AND BABATNGON, LEYTE
Category:
GAA 2025 DA FMR
Implementing office:
DPWH Tacloban City DEO · Region VIII
Contractor:
YFL BUILDERS · DPWH contractor code 41246
Contract amount:
₱49,651,613.76 (₱49.7M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IC0125 | Oct 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ISIDRO, BABATNGON, LEYTE | Completed | ₱4.9M |
| 25I00150 | Jun 11, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE (UPSTREAM), RIZAL RIVER, BABATNGON, LEYTE | On-Going | ₱123.5M |
| 25I00163 | Jun 11, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DOWNSTREAM), RIZAL RIVER, BABATNGON, LEYTE | On-Going | ₱123.7M |
| 25IC0056 | Jun 5, 2025 | NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING -TERTIARY ROADS - BAGAHUPI-BABATNGON-STA CRUZ-BARUGO-CARIGARA ROAD - K0918 + 559 - K0918 + 992, K0922 + 000 - K0922 + 380, K0922 + 401 - K0923 + 000, BABATNGON, LEYTE | On-Going | ₱53.9M |
| 25IC0192 | Jun 5, 2025 | CONCRETING OF FMR AT BRGY. PINARIGUSAN TO LIPASAN FALLS, SAN MIGUEL, LEYTE | On-Going | ₱14.9M |
| 25IC0053 | Apr 2, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - LEYTE-SAMAR INTER-PROVINCIAL ROAD - K0906 + 435 - K0906 + 676, BABATNGON, LEYTE | On-Going | ₱14.1M |
| 25IC0029 | Mar 14, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG RIZAL BRIDGE (DOWNSTREAM), BARANGAY RIZAL, BABATNGON, LEYTE | Completed | ₱96.4M |
| 25IC0007 | Feb 24, 2025 | ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - BAGAHUPI-BABATNGON-STA CRUZ-BARUGO-CARIGARA RD - K0923 + 150 - K0923 + 550, BABATNGON, LEYTE | Completed | ₱14.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.