Project 25J00219

DPWH infrastructure contract
Contract ID:
25J00219
Fingerprint:
9176215503d9a9…a9d452048c Verified
Status:
On-Going
Physical progress:
90%
Timeline:
Start May 19, 2025 (1 yr 5 mo ago)
Description:
CONSTRUCTION OF IGLOO, H15FSSU-15FSSU, KUTA HENERAL TEO-DULFO BAUTISTA, BUSBUS, JOLO, SULU, PHASE II
Category:
Buildings and Facilities
Implementing office:
DPWH Region IX · Region IX
Contractor:
AHSB CONSTRUCTION · DPWH contractor code 55648
Location:
Not stated in the source
Contract amount:
₱9,645,280.80 (₱9.6M)
Funding source:
Regular Infra - GAA 2025 CP
Budget year:
2025