Project 25JD0078

DPWH infrastructure contract
Contract ID:
25JD0078
Fingerprint:
6178a0bb86c152…b5a4d6fe29 Verified
Status:
On-Going
Physical progress:
80.4%
Timeline:
Start Aug 21, 2025 (1 yr 2 mo ago)
Description:
CONCRETING OF BRGY. LUX TO BRGY. SAS FMR, BRGY. LUX AND BRGY. SAS, GUTALAC, ZAMBOANGA DEL NORTE - MODIFIED TO: CONCRETING OF BRGY. LUX, GUTALAC, ZAMBOANGA DEL NORTE
Category:
GAA 2025 DA FMR
Implementing office:
Contractor:
JGC CONSTRUCTION & ENTERPRISES · DPWH contractor code 34305
Contract amount:
₱14,477,252.90 (₱14.5M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
23Z00033Apr 30, 2025CONTRACT PACKAGE 1C - CONSTRUCTION OF NEW TRANS-CENTRAL ROADS AND DRAINAGEOn-Going₱1.07B
25J00011Mar 14, 2025CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KIPIT RIVER AT KIPIT BR. 2 SECTION (B01183MN) ALONG LILOY-SIOCON RD (S01146MN) (DOWNSTREAM - LEFT SIOn-Going₱145.6M
25J00012Mar 14, 2025CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KIPIT RIVER AT KIPIT BR. 2 SECTION (B01183MN) ALONG LILOY-SIOCON RD (S01146MN) (UPSTREAM - LEFT SIDEOn-Going₱145.0M
25JD0005Feb 17, 2025CONSTRUCTION OF ROAD, BARANGAY LUX, GUTALAC, ZAMBOANGA DEL NORTECompleted₱14.7M
25JD0023Feb 17, 2025CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY POBLACION, GUTALAC, ZAMBOANGA DEL NORTECompleted₱11.8M
25JD0028Feb 17, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL TRIBAL HALL), GUTALAC, ZAMBOANGA DEL NORTECompleted₱4.9M
25JD0036Feb 17, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2019 + 935 - K2019 + 945, ZAMBOANGA DEL NORTECompleted₱1.9M
24J00287Jan 7, 2025ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONCRETING ALONG NRJ BARANGAY SAN ISIDRO - SAS - KALAWIT - NAMNAMA, ZAMBOANGA DEL NORTEOn-Going₱154.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.