Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25JG0039

DPWH infrastructure contract
Contract ID:
25JG0039
Fingerprint:
f2de755adb2bd0…622c2f2b67 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 13, 2025 (1 yr 7 mo ago) · Target/actual end Jan 5, 2026
Description:
CONSTRUCTION (COMPLETION) OF DPWH ZAMBOANGA DEL SUR 2ND DEO COVERED COURT, GUIPOS, ZAMBOANGA DEL SUR
Category:
GAA 2025 LFP
Implementing office:
Contractor:
NRMM CONSTRUCTION AND DEV'T CORP. · DPWH contractor code 41172
Contract amount:
₱4,884,809.02 (₱4.9M)
Funding source:
Regular Infra - GAA 2025 LFP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25JG0043Mar 28, 2025CONSTRUCTION OF DPWH ZAMBOANGA DEL SUR 2ND DEO COMPOUND, BARANGAY POBLACION, GUIPOS, ZAMBOANGA DEL SUROn-Going₱39.2M
25JG0041Mar 20, 2025CONSTRUCTION (COMPLETION) OF DPWH ZAMBOANGA DEL SUR 2ND DEO MAIN BUILDING, PUROK 1B, BARANGAY POBLACION, GUIPOS, ZAMBOANGA DEL SUROn-Going₱11.7M
25JG0040Mar 13, 2025CONSTRUCTION OF DPWH ZAMBOANGA DEL SUR 2ND DEO STAFF HOUSE, BARANGAY POBLACION, GUIPOS, ZAMBOANGA DEL SUROn-Going₱53.8M
25JG0001Feb 19, 2025NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS ROAD AND DIVERSION ROADS ALONG NRJ POBLACION GUIPOS - LINTUM, GUIPOS, ZAMBOANGA DEL SUROn-Going₱29.3M
25JG0032Feb 19, 2025NETWORK DEVELOPMENT - ROAD WIDENING - TERTIARY ROADS - ALONG JCT DUMALINAO-MARGOSATUBIG RD - K1685 + 140 - K1685 + 354, BALONGATING, GUIPOS, ZAMBOANGA DEL SUROn-Going₱7.3M
25JG0035Feb 19, 2025ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - JCT. DUMALINAO-MARGOSATUBIG RD K1689 + 190 - K1689 + 265, GUIPOS, ZAMBOANGA DEL SUROn-Going₱29.3M
24JG0051Jun 17, 2024CONSTRUCTION (COMPLETION) OF DPWH ZAMBOANGA DEL SUR 2ND DEO MAIN BUILDING, PUROK 1B, BRGY. POBLACION, GUIPOS, ZAMBOANGA DEL SURCompleted₱49.0M
24JG0016Apr 8, 2024CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF DINAS RIVER FLOOD CONTROL, BARANGAY BALONGATING, GUIPOS, ZAMBOANGA DEL SUR, PHASE IVCompleted₱19.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.