Project 25K00086

DPWH infrastructure contract
Contract ID:
25K00086
Fingerprint:
58af5dc53ecaff…8819dd11f7 Verified
Status:
On-Going
Physical progress:
86.7%
Timeline:
Start Mar 25, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) ACCESS ROAD LEADING TO NAPALIT LAKE, BRGY. PIGTAURANAN, PANGANTUCAN, BUKIDNON
Category:
GAA 2025 CP
Implementing office:
DPWH Region X · Region X
Contractor:
M. MONTESCLAROS ENTERPRISES, INC. · DPWH contractor code 6506
Contract amount:
₱9,447,488.64 (₱9.4M)
Funding source:
Regular Infra - GAA 2025 CP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25K00229May 26, 2025CONSTRUCTION OF ROAD, FROM THE NATIONAL HIGHWAY TO LUMAGWAS-KIDANGGIN ROAD LEADING TO HOT SPRINGS, PANGANTUCAN, BUKIDNONOn-Going₱95.5M
25KN0057May 23, 2025CONSTRUCTION OF RAIN WATER COLLECTION SYSTEM (RWCS) IN PUBLIC FACILITIES:Completed₱2.5M
25K00312Apr 7, 2025CONSTRUCTION OF JCT. CAMP KIBARITAN-PANGANTUCAN - JCT GUINOYURAN-VALENCIA ROAD, PANGANTUCAN SECTION, PACKAGE 5, BUKIDNONOn-Going₱189.1M
25K00267Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARAMAG-MARADUGAO RD (UPSTREAM AND DOWNSTREAM) OF MULETA BRIDGE, PACKAGE 3, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25K00268Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARAMAG-MARADUGAO RD (UPSTREAM AND DOWNSTREAM) OF MULETA BRIDGE, PACKAGE 4, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25K00269Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAGAYARAN RIVER (UPSTREAM) OF NABALIWA BRIDGE, PACKAGE 4, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25K00270Apr 4, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAGAYARAN RIVER (UPSTREAM) OF NABALIWA BRIDGE, PACKAGE 5, PANGANTUCAN, BUKIDNONOn-Going₱94.5M
25KN0015Mar 26, 2025REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS, MARAMAG - MARADUGAO RD - K1588 + 054 - K1588 + 157Completed₱2.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.