Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25K00386

DPWH infrastructure contract
Contract ID:
25K00386
Fingerprint:
7613be587e6e92…fdb18fcf60 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start May 26, 2025 (1 yr 5 mo ago)
Description:
PREVENTIVE MAINTENANCE-PRIMARY ROADS ILIGAN CITY-MARAWI CITY RD-(S01709MN) CHAINAGE 268-CHAINAGE 4200
Category:
GAA 2025 OO-1
Implementing office:
DPWH Region X · Region X
Contract amount:
₱93,929,568.85 (₱93.9M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
24K00438Aug 12, 2024CONSTRUCTION OF MUNICIPAL GYM, BRGY. POBLACION, SAGUIARAN, LANAO DEL SUROn-Going₱14.4M
24K00218May 27, 2024ROAD CONSTRUCTION BRGY. BUBONG, SAGUIARAN, LANAO DEL SUR (PHASE 2)Completed₱4.6M
24K00159May 3, 2024CONCRETING OF ROAD, BARANGAY BUBONG, SAGUIARAN, LANAO DEL SUR (PHASE 1)Completed₱9.6M
24K00139Apr 5, 2024ASSET PRESERVATION- REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS, ILIGAN CITY-MARAWI CITY RD-(S01709MN) CHAINAGE 0 - CHAINAGE 268Completed₱11.5M
23K00305Aug 7, 2023CONCRETING OF BRGY. ROAD, BRGY. POBLACION TO BRGY. MIPAGA ROAD, SAGUIARAN, LANAO DEL SURCompleted₱4.8M
23KG0011Mar 17, 2023REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES AT PANTAR BR. (B00936MN) ALONG ILIGAN CITY-MARAWI CITY RD.Completed₱1.7M
22K00172Nov 7, 2022CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BUBONG, SAGUIARAN, LANAO DEL SURCompleted₱4.8M
21K00112Nov 26, 2021ROAD WIDENING-PRIMARY ROADS, ILIGAN CITY-MARAWI CITY RD-K1554+322.668-K1555+380Completed₱50.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.