Project 25KC0073

DPWH infrastructure contract
Contract ID:
25KC0073
Fingerprint:
cba2e05add0981…7ddee13ed9 Verified
Status:
On-Going
Physical progress:
73.7%
Timeline:
Start Mar 26, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BUBUNAWAN RIVER BUBUNAWAN RIS, BAUNGON, BUKIDNON
Category:
Flood Control and Drainage
Implementing office:
Contractor:
EBCON 52 VENTURES INC · DPWH contractor code 43865
As listed: EBCON 52 VENTURES INC.
Contract amount:
₱14,302,976.36 (₱14.3M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
e5a0829a579c…Mar 19, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BUKIDNON 3RD DEO₱14,302,976.36

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26KC0041Jun 23, 2026REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG JCT. SH MANOLO FORTICH-LIBONA-INDAHAG RD. K1475+683-K1475+792, LIBONA, BUKIDNONOn-Going₱6.3M
25KC0134May 26, 2026REPAIR/REHABILITATION OF CLASSROOM, CAMP 9 ELEMENTARY SCHOOL, LIBONA, BUKIDNONOn-Going₱5.1M
25K00319Apr 7, 2025CONSTRUCTION OF ROAD, JCT. BCIR - JCT SH-MANOLO FORTICH-LIBONA-INDAHAG RD ALTERNATE DIVERSION ROAD, PACKAGE 3, BUKIDNONOn-Going₱189.1M
25K00321Apr 7, 2025CONSTRUCTION OF ROAD, JCT. BCIR - JCT SH-MANOLO FORTICH-LIBONA-INDAHAG RD ALTERNATE DIVERSION ROAD, PACKAGE 5, BUKIDNONOn-Going₱189.1M
25KC0034Mar 24, 2025PAVING OF UNPAVED ROADS ALONG JCT. SH - MANOLO FORTICH-LIBONA-INDAHAG ROAD K1476+557-K1476+826, LIBONA, BUKIDNONCompleted₱20.4M
25KC0036Mar 24, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG JCT. SH - MANOLO FORTICH-LIBONA-INDAHAG ROAD (UPSTREAM AND DOWNSTREAM) OF STA. FE BRIDGE, LIBONA, BUKIDNONCompleted₱47.9M
25KC0110Mar 18, 2025CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM BARANGAY CROSSING, SANTA FE AND PALABUCAN, LIBONA, BUKIDNONCompleted₱22.7M
25KC0111Mar 18, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, LIBONA, BUKIDNONCompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.