Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25KJ0048

DPWH infrastructure contract
Contract ID:
25KJ0048
Fingerprint:
6f1e9d72963234…be1f49ee21 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 9, 2025 (1 yr 4 mo ago) · Target/actual end Aug 1, 2026
Description:
CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (BARANGAY COVERED COURT), BRGY. MAQUILAO, TANGUB CITY, MISAMIS OCCIDENTAL
Category:
GAA 2025 SSP
Implementing office:
Contractor:
ANGEL & SAM CONSTRUCTION & GEN. MDSE. · DPWH contractor code 19968
Contract amount:
₱2,413,115.01 (₱2.4M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25KJ0046Sep 16, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (BARANGAY HEALTH STATION), BRGY. BALATACAN, TANGUB CITY, MISAMIS OCCIDENTALCompleted₱2.5M
25KJ0056Jul 21, 2025CONSTRUCTION OF OVERPASS, BRGY. PANGABUAN, TANGUB CITY, MISAMIS OCCIDENTALCompleted₱14.6M
25KJ0103Jul 21, 2025CONSTRUCTION OF ROAD CANAL, BRGY. STO. NIÑO, TANGUB CITY, MISAMIS OCCIDENTALCompleted₱4.8M
25KJ0024Jul 9, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (BARANGAY HEALTH STATION), BRGY. SALIMPUNO, TANGUB CITY, MISAMIS OCCIDENTALOn-Going₱2.4M
25KJ0025Jul 9, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (BARANGAY HEALTH STATION), BRGY. PANALSALAN, TANGUB CITY, MISAMIS OCCIDENTALOn-Going₱2.4M
25KJ0047Jul 9, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (BARANGAY HEALTH STATION), BRGY. BOCATOR, TANGUB CITY, MISAMIS OCCIDENTALOn-Going₱2.4M
25KJ0049Jul 9, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (BARANGAY HEALTH STATION), BRGY. GUINABOT, TANGUB CITY, MISAMIS OCCIDENTALCompleted₱2.4M
25KJ0104Jul 9, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS PANGUIL BAY COASTAL ROAD (OZAMIZ - TANGUB SECTION)Completed₱47.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.