Project 25LD0124
DPWH infrastructure contract
Contract ID:
25LD0124
Fingerprint:
0421e97d4d6e50…e5b612b464 Verified
Status:
On-Going
Physical progress:
98.4%
Timeline:
Start Mar 26, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF FLOOD MITIGATING STRUCTURE WITH STEEL SHEET PILE ALONG PADADA MAINIT RIVER (MASALAM BRIDGE-LAPULABAO SECTION0, HAGONOY, DAVAO DEL SUR
Category:
GAA 2025 OO-2
Implementing office:
DPWH Davao del Sur DEO · Region XI
Contractor:
ROAD EDGE TRADING AND DEVELOPMENT SERVICES · DPWH contractor code 33140
As listed: ROAD EDGE TRADING & DEVELOPMENT SERVICES
Contract amount:
₱95,484,992.40 (₱95.5M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| dcd188679b46… | Mar 25, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DAVAO DEL SUR DIST | ₱95,484,992.40 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26LD0001 | Jun 30, 2026 | CONSTRUCTION OF CONCRETE ROAD-ACCESS ROAD FROM WATERFALL ROAD LEADING TO PANDONG BATO TRAIL, STA. 1+700.00- STA. 1+850.00, KIBLAWAN, DAVAO DEL SUR | On-Going | ₱4.1M |
| 26LD0014 | Jun 30, 2026 | CONSTRUCTION OF CONCRETE ROAD-ACCESS ROAD LEADING TO PULA TANA VIEWING DECK, STA. 2+502.83-STA. 2+741.30, KIBLAWAN, DAVAO DEL SUR | On-Going | ₱4.2M |
| 25LD0053 | Jun 3, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM- LEVEL II, BARANGAY KIMLAWIS, KIBLAWAN, DAVAO DEL SUR | Completed | ₱4.9M |
| 25L00080 | Apr 10, 2025 | ROAD WIDENING - BYPASS ROAD, JCT. PADADA (ALONG DIGOS - MAKAR ROAD) - KIBLAWAN - JCT. MALUNGON (ALONG DIGOS - MAKAR ROAD), PACKAGE I, DAVAO DEL SUR | On-Going | ₱86.2M |
| 25LD0089 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. LATIAN, KIBLAWAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 25LD0098 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. COGON, BACACA, KIBLAWAN, DAVAO DEL DUR | Completed | ₱4.8M |
| 25LD0104 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. SAN PEDRO, KIBLAWAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 25LD0107 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. BAGONG NEGROS, KIBLAWAN, DAVAO DEL SUR | On-Going | ₱5.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.