Project 25LD0207

DPWH infrastructure contract
Contract ID:
25LD0207
Fingerprint:
4a64266037b6c5…2ec4929edd Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 26, 2025 (1 yr 7 mo ago) · Target/actual end Mar 2, 2026
Description:
CONCRETING OF BRGY. BULACAN FMR, BRGY. BULACAN, MALALAG, DAVAO DEL SUR
Category:
GAA 2025 DA FMR
Implementing office:
Contractor:
CMBUEN CONSTRUCTION SERVICES · DPWH contractor code 50465
Contract amount:
₱14,447,173.03 (₱14.4M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25L00126Sep 12, 2025CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - MAHARLIKA HIGHWAY (DIGOS - MAKAR RD.) - K1589+861 - K1569+903, K1590+000 - K1590+224, DAVAO DEL SUROn-Going₱97.3M
25LD0173Jun 25, 2025CONSTRUCTION OF FLOOD MITIGATING STRUCTURE (CONCRETE REVETMENT/DIKE) ALONG MALALAG RIVER( STEEL BRIDGE, PUROK 2 & PUROK 3 SECTION), BRGY. IBO, MALALAG, DAVAO DEL SUROn-Going₱96.0M
25LD0146Jun 9, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE-CONCRETE REVETMENT ALONG PADADA-MAINIT RIVER (LAPULABAO-MASALAM BRIDGE DOWNSTREAM SECTION) HAGONOY, DAVAO DEL SURCompleted₱120.0M
25ME0009Mar 31, 2025NHW JCT. MALUNGON GAMAY - KIBAWALAN - PUROK ONSE LEADING TO BUSAGAN FALLS, MALUNGON, SARANGANI PROVINCECompleted₱9.5M
25LD0065Mar 24, 2025CONSTRUCTION OF FLOOD MITIGATING STRUCTURE ALONG MALALAG RIVER (IBO-PITO SECTION), BARANGAY IBO, MALALAG, DAVAO DEL SUROn-Going₱47.5M
25LD0071Mar 24, 2025PREVENTIVE MAINTENANCE OF ROAD; ASPHALT OVERLAY- DAVAO- SARANGANI COASTAL RD ( MALALAG- MALITA-JAS-G)- K1595+445-K1596+042, DAVAO DEL SUROn-Going₱24.9M
25LD0081Mar 24, 2025CONSTRUCTION (COMPLETION) OF MPB, BRGY. BOLTON, MALALAG, DAVAO DEL SURCompleted₱3.0M
25LD0132Mar 24, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, DSSF, MALALAG, DAVAO DEL SUROn-Going₱7.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.