Project 25LF0148
DPWH infrastructure contract
Contract ID:
25LF0148
Fingerprint:
cdf959521e2196…854329718b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 9, 2025 (1 yr 5 mo ago) · Target/actual end Jun 29, 2025
Description:
INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS) ALONG SURIGAO DEL SUR BDRY-DAVAO OR COASTAL RD- K1657+000-K1658+703 MANAY, DAVAO ORIENTAL
Category:
GAA 2025 SSP
Implementing office:
DPWH Davao Oriental 1st DEO · Region XI
Contractor:
FZI CONSTRUCTION PARTS AND SUPPLY CO. · DPWH contractor code 42232
Contract amount:
₱648,908.34 (₱648.9K)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25LF0130 | Jun 9, 2025 | CONSTRUCTION OF COASTAL PROTECTION, PROTECTING SURIGAO DEL SUR BDRY.- DAVAO ORIENTAL COASTAL RD. (PINAKPAKAN SECTION), MANAY, DAVAO ORIENTAL | On-Going | ₱142.6M |
| 25LF0143 | Jun 9, 2025 | CONSTRUCTION OF ROAD, FROM JUNCTION TO SITIO MIDSAYAP, BARANGAY OLD MACOPA MANAY, DAVAO ORIENTAL | On-Going | ₱95.0M |
| 25LF0025 | Apr 8, 2025 | SAN IGNACIO BYPASS ROAD, DAVAO ORIENTAL | On-Going | ₱88.0M |
| 25LF0031 | Apr 8, 2025 | NHJ-LINGAYAO TO SITIO SUMANDING OF BRGY. SAN IGNACIO CONNECTING MANAY PUBLIC TERMINAL TO COCONUT PROCESSING, MANAY, DAVAO ORIENTAL | Completed | ₱6.9M |
| 25LF0077 | Apr 8, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM COVERED COURT) SITIO LIBUAC BARANGAY OLD MACOPA MANAY, DAVAO ORIENTAL | Completed | ₱7.9M |
| 25LF0083 | Apr 8, 2025 | CONSTRUCTION OF EVACUATION CENTER, BARANGAY MABINI MANAY, DAVAO ORIENTAL | Completed | ₱7.8M |
| 25LF0047 | Apr 7, 2025 | CONSTRUCTION OF ROAD, FROM POBLACION TO PUROK DANGO, BARANGAY MANREZA, MANAY, DAVAO ORIENTAL | Completed | ₱4.9M |
| 25LF0048 | Apr 7, 2025 | CONSTRUCTION OF ROAD, FROM SITIO GUICOB TO PUROK BASIO TO PUROK MAPAYO, BARANGAY SAN IGNACIO, MANAY, DAVAO ORIENTAL | Completed | ₱5.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.