Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25LG0002

DPWH infrastructure contract
Contract ID:
25LG0002
Fingerprint:
4185045e2bef7f…62744237d0 Verified
Status:
On-Going
Physical progress:
96.4%
Timeline:
Start Mar 26, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF CONCRETE REVETMENT ALONG SUMLOG RIVER, BARANGAY CABADIANGAN-COCORNON-LANGKA, LUPON, DAVAO ORIENTAL
Category:
GAA 2025 OO-2
Implementing office:
Contractor:
Contract amount:
₱92,443,242.41 (₱92.4M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25LG0051Aug 21, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- PRES. DIOSDADO P. MACAPAGAL NAT'L HI-WAY 1748+500-K1749+184, K1749 + 506 - K1750 +142On-Going₱95.5M
25LG0072Aug 21, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG LOGDECK RIVER, LUPON, DAVAO ORIENTALOn-Going₱98.0M
25LG0073Jul 7, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PANGYAN UPPER SUMLOG RIVER, LUPON, DAVAO ORIENTALOn-Going₱97.0M
25LG0033May 26, 2025PREVENTIVE MAINTENANCE OF ROAD:ASPHALT OVERLAY-PRES. DIOSDADO P. MACAPAGAL NATL HI-WAY-K1745+281-K1746+299,K1748+122-K1748+500Completed₱96.5M
25LG0010Mar 27, 2025CONSTRUCTION OF LONGCALOB BRIDGE APPROACHES , NEW VISAYAS- SAN ISIDRO-LONGCALOB ROAD, LUPON, DAVAO ORIENTALOn-Going₱28.8M
25LG0025Mar 27, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, DONCAMAR, LUPON, DAVAO ORIENTALOn-Going₱93.6M
25LG0062Mar 27, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, PACKAGE 2, LUPON, DAVAO ORIENTALOn-Going₱5.4M
25LG0064Mar 27, 2025CONSTRUCTION OF MULTI -PURPOSE BUILDING, PACKAGE 3, LUPON, DAVAO ORIENTALOn-Going₱8.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.