Project 25LJ0132

DPWH infrastructure contract
Contract ID:
25LJ0132
Fingerprint:
82f18056ad5b76…cdcbca7256 Verified
Status:
On-Going
Physical progress:
80.2%
Timeline:
Start Jul 4, 2025 (1 yr 4 mo ago)
Description:
CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE (EARTH DIKE) ALONG TAGUM LIBUGANON RIVER BASIN, CARMEN - B.E. JUALI, STO. TOMAS, DAVAO DEL NORTE, SECTION 3, DAVAO DEL NORTE
Category:
GAA 2025 SSP
Implementing office:
Contractor:
Contract amount:
₱96,019,762.66 (₱96.0M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26LJ0025Jun 4, 2026JCT. ROAD TUGANAY - DUJALI - KINAMAYAN TO POB NEW CASAY, RJS PUROK 5, POB CABAYANGAN TO PUROK SAMPAGUITA LEADING TO PALAYAMANAN, BRGY. CABAY-ANGAN, B.E. DUJALI, DAVAO DEL NORTE - 0+000 - 0+270Completed₱3.7M
26LJ0013May 25, 2026TANGLAW BR. 1 (B00188MN) ALONG TAGUM-PANABO CIRCUM RDOn-Going₱7.7M
26LJ0015May 25, 2026TANGLAW BR. 4 (B00185MN) ALONG TAGUM-PANABO CIRCUM RDOn-Going₱8.6M
26LJ0010May 14, 2026LOCUTAN BR. 2 (B02213MN) ALONG TAGUM-PANABO CIRCUM RDOn-Going₱2.9M
25LJ0131Jul 4, 2025CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE (EARTH DIKE) ALONG TAGUM LIBUGANON RIVER BASIN, CARMEN - B.E. JUALI, STO. TOMAS, DAVAO DEL NORTE, SECTION 2, DAVAO DEL NORTEOn-Going₱97.0M
25LJ0135Jul 4, 2025CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE (EARTH DIKE) ALONG TAGUM LIBUGANON RIVER BASIN, CARMEN - B.E. JUALI, STO. TOMAS, DAVAO DEL NORTE, SECTION 1, DAVAO DEL NORTEOn-Going₱97.2M
25LJ0147Mar 26, 2025CONCRETING OF FARM TO MARKET ROAD, PUROK 4, D-5, BARANGAY DUJALI RO PUROK 3, BUGTONG TALISAY BARANGAY DUJALI, BRAULIO E. DUJALI, DAVAO DEL NORTECompleted₱48.2M
25LJ0025Mar 21, 2025JCT. ROAD TUGANAY-DUJALI-KINAMAYAN TO POB NEW CASAY, RJS PUROK 5, POB CABAYANGAN TO PUROK SAMPAGUITA LEADING TO PALAYAMANAN, BARANGAY CABAY-ANGAN, B.E. DUJALI, DAVAO DEL NORTECompleted₱4.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.