Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25M00050

DPWH infrastructure contract
Contract ID:
25M00050
Fingerprint:
5d4e307231c9c0…14802f34e4 Verified
Status:
On-Going
Physical progress:
85.6%
Timeline:
Start Jul 9, 2025 (1 yr 4 mo ago)
Description:
PREVENTIVE MAINTENANCE - MAHARLIKA HIGHWAY (COTABATO-MARBEL RD) - K1738 + 462 - K1740 + 000, SURALLAH, SOUTH COTABATO
Category:
GAA 2025 OO-1
Implementing office:
DPWH Region XII · Region XII
Contractor:
Contract amount:
₱205,760,657.73 (₱205.8M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26MG0009Jun 11, 2026PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1740+504-K1740+949On-Going₱16.3M
25MG0107Aug 20, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, SOCCSKSARGEN GENERAL HOSPITAL, DAJAY, SURALLAH, NORTH COTABATOCompleted₱19.5M
25MG0089Jun 20, 2025CONSTRUCTION OF MULTI PURPOSE BUILDING AT BARANGAY DAJAY, SURALLAH, SOUTH COTABATOCompleted₱4.9M
24M00028Jun 13, 2025CONSTRUCTION OF THREE STOREY COLLEGE LIBRARY-SOUTH COTABATO STATE COLLEGE, SURALLAH, SOUTH COTABATOCompleted₱14.9M
25MG0018Apr 11, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1733+867-K1734+975, SOUTH COTABATOCompleted₱45.0M
25MG0022Mar 3, 2025CONSTRUCTION OF CONCRETE ROAD-SITIO MORALES, BRGY. CENTRALA-SITIO PULA, BRGY. TUBI-ALA ROAD IN SUPPORT TO FOOD INDUSTRY (SUGARCANE, BANANA, MONGGO, FISH AND VEGETABLES) IN SURALLAH, SOUTH COTABATOCompleted₱24.4M
25MG0007Feb 28, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1740+052-K1740+594, SOUTH COTABATOCompleted₱24.0M
25MG0008Feb 28, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1742+848-K1743+423, SOUTH COTABATOCompleted₱9.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.