Project 25MD0059
DPWH infrastructure contract
Contract ID:
25MD0059
Fingerprint:
9fc20910a47f92…2bf3762ab4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 7, 2025 (1 yr 4 mo ago) · Target/actual end Jul 9, 2026
Description:
JCT. DAVAO - COTABATO (CROSSING BAGUER) - SITIO DALUMANGKOM - SITIO LAMPAKI ROAD, PIGKAWAYAN, NORTH COTABATO
Category:
GAA 2025 CP
Implementing office:
DPWH Cotabato 1st DEO · Region XII
Contractor:
LLABAN CONSTRUCTION & SUPPLY (FORMERLY: LLABAN CON · DPWH contractor code 29504
Contract amount:
₱65,516,745.00 (₱65.5M)
Funding source:
Regular Infra - GAA 2025 CP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MD0044 | Jul 28, 2025 | CONSTRUCTION OF ROAD, SITIO PINAMULAAN - BARANGAY NORTH MANUANGAN - BARANGAY SOUTH MANUANGAN, PIGCAWAYAN, NORTH COTABATO | Completed | ₱4.9M |
| 25MD0012 | Mar 6, 2025 | CONSTRUCTION OF ROAD JCT. HIGHWAY - BULUAN ROAD, BARANGAY BULUAN, PIGCAWAYAN, NORTH COTABATO | Completed | ₱4.9M |
| 25MD0030 | Mar 6, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY CAPAYURAN, PIGCAWAYAN, NORTH COTABATO | Completed | ₱4.9M |
| 25MD0031 | Feb 27, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BALOGO RIVER, UPSTREAM OF BALOGO BRIDGE, BARANGAY BALOGO, PIGCAWAYAN, COTABATO | Completed | ₱94.7M |
| 25MD0038 | Feb 27, 2025 | CONSTRUCTION OF BALOGO RIVER FLOOD CONTROL STRUCTURE, ANICK SECTION, BARANGAY ANICK, PIGCAWAYAN, COTABATO | Completed | ₱94.4M |
| 24MD0066 | May 15, 2024 | CONCRETING OF BRGY. MALU-AU TO BRGY. NEW CULASI FMR, BRGY. MALU-AU AND BRGY. NEW CULASI, PIGCAWAYAN, COTABATO | Completed | ₱9.9M |
| 24MD0075 | May 15, 2024 | CONCRETING OF BRGY. BALOGO TO SITIO PAGLAUM FMR, BRGY. BALOGO, PIGCAWAYAN, COTABATO | Completed | ₱9.9M |
| 24MD0061 | Apr 26, 2024 | CONSTRUCTION OF 1 UNIT, 1-STOREY 2-CLASSROOM SCHOOL BUILDING, CORNELIO V. COCAL ELEMENTARY SCHOOL, BARANGAY BAGUER, LIBUNGAN, COTABATO | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.