Project 25ME0004
DPWH infrastructure contract
Contract ID:
25ME0004
Fingerprint:
66a8a236d5117b…e74d257091 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 31, 2025 (1 yr 7 mo ago) · Target/actual end Dec 3, 2025
Description:
ASPHALT OVERLAY ALONG SARANGANI - SULTAN KUDARAT COASTAL RD K1745+320 - K1746+032, K1746+085 - K1747+000, KIAMBA, SARANGANI PROVINCE
Category:
GAA 2025 OO-1
Implementing office:
DPWH Sarangani DEO · Region XII
Contractor:
MGBJ RISING CONSTRUCTION AND LAND DEVELOPER · DPWH contractor code 18656
As listed: MGBJ RISING CONSTRUCTION & LAND DEVELOPER
Contract amount:
₱63,590,116.46 (₱63.6M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| f0d21c00d868… | Mar 24, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SARANGANI DISTRICT E | ₱63,590,116.46 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ME0103 | Sep 19, 2025 | CONSTRUCTION OF SALAKIT MULTI-PURPOSE BUILDING (BARANGAY HALL), SALAKIT, KIAMBA, SARANGANI PROVINCE | Completed | ₱5.9M |
| 25ME0119 | Sep 15, 2025 | CONSTRUCTION/ COMPLETION OF MUTI-PURPOSE BUILDING, KIAMBA, SARANGANI PROVINCE | Completed | ₱2.9M |
| 25ME0111 | Aug 15, 2025 | CONSTRUCTION OF LOMUYON MULTI-PURPOSE BUILDING (BARANGAY HALL), LOMUYON, KIAMBA, SARANGANI PROVINCE | Completed | ₱5.9M |
| 25ME0117 | Aug 15, 2025 | ASPHALT OVERLAY - SARANGANI - SULTAN KUDARAT COASTAL ROAD K1720+930 - K1722+748, KIAMBA, SARANGANI PROVINCE | Completed | ₱68.5M |
| 25ME0118 | Aug 15, 2025 | ASPHALT OVERLAY - SARANGANI - SULTAN KUDARAT COASTAL RD K1717+506 - K1720+000, KIAMBA, SARANGANI PROVINCE | Completed | ₱105.9M |
| 25ME0080 | Jul 15, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, NEW LA UNION, MAITUM, SARANGANI PROVINCE | Completed | ₱39.2M |
| 25ME0068 | May 30, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BRGY. KAPATE, KIAMBA, SARANGANI PROVINCE | Completed | ₱4.5M |
| 25ME0003 | Mar 31, 2025 | ASPHALT OVERLAY ALONG SARANGANI - SULTAN KUDARAT COASTAL RD K1739+911 - K1742+665, KIAMBA, SARANGANI PROVINCE | Completed | ₱108.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.