Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25ME0011

DPWH infrastructure contract
Contract ID:
25ME0011
Fingerprint:
dbd412a0d7eb44…d28a99872d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 31, 2025 (1 yr 7 mo ago) · Target/actual end Jun 20, 2025
Description:
ROAD ALKIKAN - DATAL BATONG - DATAL BILA IN SUPPORT OF AGRO - INDUSTRIES, MALUNGON, SARANGANI PROVINCE
Category:
Roads
Implementing office:
DPWH Sarangani DEO · Region XII
Contractor:
GRECO CONSTRUCTION AND SUPPLY · DPWH contractor code 21884
Contract amount:
₱4,751,381.27 (₱4.8M)
Funding source:
Regular Infra - GAA 2025 CP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
736adc6e4b69…Mar 24, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SARANGANI DISTRICT E₱4,751,381.27

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25ME0120Sep 19, 2025COMPLETION OF SITIO DATAL BACA MULTI-PURPOSE BUILDING, DATAL BATONG, MALUNGON, SARANGANI PROVINCECompleted₱4.9M
25ME0107Aug 15, 2025CONSTRUCTION (COMPLETION) TAMBAN SOLAR WATER SYSTEM, MALUNGON, SARANGANI PROVINCECompleted₱3.0M
25M00010Aug 14, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) -K1621+450 - K1621+459, MALUNGON, SARANGANIOn-Going₱8.0M
25M00009Aug 6, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) -K1603+200 - K1603+229, MALUNGON, SARANGANIOn-Going₱30.0M
25LE0039Jul 17, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DATU INTAN, STA. MARIA, DAVAO OCCIDENTALOn-Going₱4.9M
25ME0079Jul 15, 2025REHABILITATION OF MALUNGON MUNICIPAL GYMNASIUM, POBLACION, MALUNGON, SARANGANI PROVINCEOn-Going₱40.6M
25M00013Jul 4, 2025ROAD WIDENING - MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) - K1612+961 - K1613+532, K1613+590 - K1613+996, K1620+098 - K1620+322 MALUNGON, SARANGANIOn-Going₱47.3M
25ME0061May 30, 2025CONSTRUCTION OF BUAYAN RIS, PROPOSED 800M PROTECTION WORKS AT DOWNSTREAM AND UPSTREAM OF NIA DIVERSION WORKS (300M BOTH SIDES D/S AND 200M BOTH SIDES U/S, MALUNGON, SARANGANI PROVINCECompleted₱14.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.