25MG0021
Fingerprint:
2379f4753db5b2…d395787f02 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 11, 2025 (1 yr 7 mo ago) · Target/actual end Dec 2, 2025
Description:
PAVING OF UNPAVED ROADS-SURALLAH-LAKE SEBU-MAITUM RD-K1781+200-K1781+404.90, K1781+430.90-K1781+470.90, SOUTH COTABATO
Category:
GAA 2025 OO-1
Implementing office:
DPWH South Cotabato 2nd DEO · Region XII
Contractor:
GOLDEN A NINE CONSTRUCTION · DPWH contractor code 46558
Contract amount:
₱7,774,235.75 (₱7.8M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 0be353b83220… | Mar 27, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH COTABATO 2ND | ₱7,774,235.75 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26MG0017 | Jun 17, 2026 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE-SURALLAH-LAKE SEBU-MAITUM RD-K1745+300-K1745+453 | On-Going | ₱35.2M |
| 26MG0010 | Jun 11, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1757+291-K1757+760 | On-Going | ₱9.1M |
| 26MG0012 | Jun 11, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1759+000-K1761+020 | Completed | ₱21.9M |
| 26MG0011 | Jun 4, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1755+815-K1757+291 | Completed | ₱19.7M |
| 25MG0112 | Aug 20, 2025 | CONSTRUCTION OF SCHOOL BUILDING, UBO ELEMENTARY SCHOOL-LAMFENEK EXTENSION, BARANGAY LAMFUGON, LAKE SEBU, SOUTH COTABATO | Completed | ₱5.0M |
| 25M00052 | Aug 5, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SURALLAH-LAKE SEBU-MAITUM RD - K1799+460 - K1799+580, K1827+970 - K1828+022, LAKE SEBU, SOUTH COTABATO | On-Going | ₱93.6M |
| 25MG0110 | Jun 27, 2025 | CLUSTER I-A.CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), KIANTAY ELEMENTARY SCHOOL, SITIO KIANTAY, BRGY. UPPER SEPAKA, SURALLAH, SOUTH COTABATO B.CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), NEW TUPI IS, SITIO NEW TUPI, BRGY. NED, LAKE SEBU, S | Completed | ₱2.6M |
| 25MG0016 | Apr 11, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1755+262-K1755+815, SOUTH COTABATO | Completed | ₱13.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.