Project 25MH0094
DPWH infrastructure contract
Contract ID:
25MH0094
Fingerprint:
5362f9f714ddbb…dd2886f1d9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 21, 2025 (1 yr 7 mo ago) · Target/actual end Jul 31, 2025
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, PALIMBANG, SULTAN KUDARAT
Category:
Buildings and Facilities
Implementing office:
DPWH Sultan Kudarat 2nd DEO · Region XII
Contractor:
JV CONSTECH · DPWH contractor code 35974
Contract amount:
₱4,801,490.40 (₱4.8M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MH0124 | Aug 19, 2025 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM | Completed | ₱2.6M |
| 25MH0022 | Mar 25, 2025 | CONSTRUCTION OF RIVER BANK PROTECTION (UPSTREAM LEFT SIDE), BARANGAY BARONGIS, PALIMBANG, SULTAN KUDARAT | Completed | ₱120.6M |
| 25MH0090 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), BALIANGO ELEMENTARY SCHOOL, BARANGAY BALIANGO, PALIMBANG, SULTAN KUDARAT | Completed | ₱3.8M |
| 25MH0092 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), BARANGAY KOLONGKOLONG, PALIMBANG, SULTAN KUDARAT | Completed | ₱2.9M |
| 25MH0003 | Mar 19, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K1998+000 - K1999+197 | Completed | ₱21.0M |
| 25MH0004 | Mar 19, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K2006+000 - K2006+892 | Completed | ₱15.7M |
| 25MH0005 | Mar 17, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K2029+246 - K2030+000, K2044+087 - K2044+387 | Completed | ₱18.4M |
| 25MH0088 | Mar 11, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), BALUAN CENTRAL ELEMENTARY SCHOOL, BARANGAY BALUAN, PALIMBANG, SULTAN KUDARAT | Completed | ₱3.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.