Project 25MH0133
DPWH infrastructure contract
Contract ID:
25MH0133
Fingerprint:
cc52d8414594ee…c32f23bee8 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Jan 9, 2026 (10 mos ago)
Description:
REPAIR/REHABILITATION OF CLASSROOMS, MASIAG CENTRAL SCHOOL, BAGUMBAYAN, SULTAN KUDARAT
Category:
GAA 2025 DEPED BEFF
Implementing office:
DPWH Sultan Kudarat 2nd DEO · Region XII
Contractor:
DINGO BUILDERS AND SUPPLY · DPWH contractor code 37794
Contract amount:
₱5,190,391.67 (₱5.2M)
Funding source:
Outside Infra - GAA 2025 DEPED BEFF
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26MH0001 | Jun 11, 2026 | RECONSTRUCTION TO CONCRETE PAVEMENT - ISULAN JCT-NINOY AQUINO RD - K1807+361 - K1807+439, K1808+100 - K1808+300 | On-Going | ₱4.7M |
| 25MH0116 | May 7, 2026 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), BAGUMBAYAN CENTRAL ELEMENTARY SCHOOL, BARANGAY POBLACION, BAGUMBAYAN, SULTAN KUDARAT | On-Going | ₱2.0M |
| 25MH0112 | Nov 11, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, BAGUMBAYAN, SULTAN KUDARAT | Completed | ₱2.0M |
| 25MH0113 | Nov 6, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), MASIAG CENTRAL ELEMENTARY SCHOOL, BARANGAY MASIAG, BAGUMBAYAN, SULTAN KUDARAT | Completed | ₱1.9M |
| 25MH0016 | Mar 25, 2025 | REHABILITATION/MAJOR REPAIR OF BRIDGE - BAGUMBAYAN BR. (B00608MN) ALONG ISULAN JCT. - NINOY AQUINO RD (PHASE II) | Completed | ₱23.6M |
| 25MH0023 | Mar 25, 2025 | CONSTRUCTION OF RIVER BANK PROTECTION AT BAGUMBAYAN RIVER, BARANGAY POBLACION, BAGUMBAYAN, SULTAN KUDARAT | Completed | ₱121.7M |
| 25MH0048 | Mar 25, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), BARANGAY SANTO NIÑO, BAGUMBAYAN, SULTAN KUDARAT | Completed | ₱2.9M |
| 25MH0046 | Mar 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM), BARANGAY MASIAG, BAGUMBAYAN, SULTAN KUDARAT | Completed | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.