Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25MI0016

DPWH infrastructure contract
Contract ID:
25MI0016
Fingerprint:
ab13cc803b8adb…a38d6f618a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 23, 2025 (1 yr 5 mo ago) · Target/actual end Sep 16, 2025
Description:
INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (GUARDRAILS, PAVEMENT MARKINGS, ROAD SIGNS) ALONG BUKIDNON-COTABATO RD - K1642+(-177) - K1643+334, K1642+(-334) - K1642+(-177), K1642+(-468) - K1643+(-334), K1642+(-660) - K1642+(-468), K1643+334 - K1655+
Category:
GAA 2025 SSP
Implementing office:
DPWH Cotabato 3rd DEO · Region XII
Contract amount:
₱36,207,396.24 (₱36.2M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
35106174120e…May 15, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAY COTABATO 3RD DEO₱36,207,396.24

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26MI0060Jun 18, 2026RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG BUKIDNON-COTABATO RD - K1629 + 530 - K1629 + 625Completed₱53.1M
26MI0007Jun 17, 2026(RE-BID) ASPHALT OVERLAY ALONG BUKIDNON-COTABATO RD - K1611 + 000 - K1611 + 620Completed₱18.7M
26MI0010May 7, 2026ROAD WIDENING ALONG BUKIDNON-COTABATO RD - K1625 + 716 - K1627 + 175On-Going₱40.8M
25MI0030Aug 19, 2025BUKIDNON-COTABATO RD - K1630 + 100 - K1630 + 300Completed₱79.3M
25MI0031Aug 19, 2025BUKIDNON-COTABATO RD - K1629 + 625 - K1629 + 905Completed₱105.6M
25MI0056Aug 19, 2025BUKIDNON-COTABATO RD - K1612+656 - K1613+000On-Going₱127.8M
25MI0089Jul 29, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) IN BRGY. UGALINGAN, CARMEN, COTABATOCompleted₱4.7M
25MI0090Jul 29, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) IN BRGY. LILIONGAN, CARMEN, COTABATOCompleted₱4.7M