Project 25NA0051
DPWH infrastructure contract
Contract ID:
25NA0051
Fingerprint:
8f459aa93e54e0…bc99704ae9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 19, 2026 (7 mos ago) · Target/actual end Sep 14, 2026
Description:
CONSERVATION AND RESTORATION OF GABALDON AND OTHER HERITAGE SCHOOL BUILDINGS - NORTH CABADBARAN CES, CITY OF CABADBARAN, AGUSAN DEL NORTE
Category:
GAA 2025 DepEd Conservation and Restoration of Gabaldon and Other Heritage School Buildings
Implementing office:
DPWH Agusan del Norte DEO · Region XIII
Contractor:
JD-RG CONSTRUCTION AND SUPPLIES CORP. · DPWH contractor code 39586
As listed: JD-RG CONSTRUCTION AND SUPPLIES CORP. (FORMERLY: JD-RG CONSTRUCTION CORPORATION)
Contract amount:
₱7,995,456.59 (₱8.0M)
Funding source:
Outside Infra - GAA 2025 DepEd Conservation and Restoration of Gabaldon and Other Heritage School Buildings
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25N00022 | Sep 15, 2025 | MAHARLIKA HIGHWAY (AGUSAN-DAVAO SECT)- K1255+492 - K1257+004, K1272+587- K1273+420 | On-Going | ₱136.2M |
| 25NA0042 | Jul 10, 2025 | (CLUSTER) RAINWATER COLLECTOR SYSTEM, AGUSAN DEL NORTE | Completed | ₱2.6M |
| 25NA0039 | May 28, 2025 | CONSTRUCTION OF SCHOOL BUILDING, COMAGASCAS ELEMENTARY SCHOOL, BRGY. COMAGASCAS, CABADBARAN CITY, AGUSAN DEL NORTE | Completed | ₱9.6M |
| 25NA0040 | May 28, 2025 | CONSTRUCTION OF SCHOOL BUILDING, CONCEPCION INTEGRATED SCHOOL, BRGY. CONCEPCION, CABADBARAN CITY, AGUSAN DEL NORTE | Completed | ₱8.6M |
| 25N00091 | Apr 10, 2025 | CONSTRUCTION OF ROAD, PACKAGE 2, TELESFORA-CAMINGAWAN-CANTICOL, TUBAY, AGUSAN DEL NORTE | Completed | ₱48.9M |
| 25NA0013 | Mar 24, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, CALIBUNAN CREEK FROM PUROK 4 TO PUROK 11, BARANGAY CALIBUNAN, CABADBARAN CITY, AGUSAN DEL NORTE | Completed | ₱9.8M |
| 25NA0015 | Mar 24, 2025 | CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, NRJ-COMAGASCAS-DEL PILAR-PIRADA LEADING TO TUNNEL ROAD, BRGY. DEL PILAR, CABADBARAN, AGUSAN DEL NORTE | Completed | ₱24.5M |
| 25N00131 | Mar 20, 2025 | CABADBARAN - PUTING BATO - LANUZA ROAD, PACKAGE 11, AGUSAN DEL NORTE | Completed | ₱48.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.