FY2026 GAA: ₱6.79T
PisoScan

Project 25NH0127

DPWH infrastructure contract
Contract ID:
25NH0127
Fingerprint:
dfe8df963a09ec…b6b1f8e934 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 14, 2025 (1 yr 3 mo ago) · Target/actual end Sep 4, 2025
Description:
PACKAGE 1 - CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RCWS) SURIGAO DEL SUR
Category:
GAA 2025 LS Itemization
Implementing office:
Contractor:
TRIDENT ENGINEERING SERVICES · DPWH contractor code 47939
Contract amount:
₱2,576,648.74 (₱2.6M)
Funding source:
Regular Infra - GAA 2025 LS Itemization
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26NH0001Aug 26, 2026SURIGAO-DAVAO COASTAL RD - K1321 + 000 - K1323 + 190, K1323 + 232 - K1323 + 755On-Going₱94.1M
25NH0126Sep 12, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL GYMNASIUM), BAYABAS, SURIGAO DEL SUROn-Going₱24.5M
25NH0101Jun 11, 2025CONCRETING OF CABUGO, BAYABAS TO TAWAGAN, CAGWAIT ROAD, SURIGAO DEL SUROn-Going₱24.1M
25NH0063Apr 10, 2025CONSTRUCTION OF TAGO RIS (BALISONG DAM) PROTECTION WORKS ALONG BALISONG RIVER, TAGO,SURIGAO DEL SURCompleted₱29.4M
25NH0033Apr 7, 2025SURIGAO-DAVAO COASTAL RD - K1324 + 050 - K1324 + 110, K1325 + 000 - K1325 + 241, K1327 + 514 - K1327 + 591, K1329 + 810 - K1329 + 878On-Going₱7.7M
24NH0052Sep 5, 2024CONSTRUCTION OF FLOOD CONTROL STRUCTURE OF PAGBAHANAN RIVER DIKE AT BARANGAY MAGOBAWOK, BAYABAS, SURIGAO DEL SURCompleted₱48.2M
24NH0049Jun 21, 2024CONSTRUCTION OF COASTAL ROAD FROM SITIO HINAPLIAN BALETE TO PUROK 2, BAYABAS, SURIGAO DEL SURCompleted₱34.3M
24NH0009Jun 3, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CABUGO, BAYABAS, SURIGAO DEL SURCompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.