Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25OB0019

DPWH infrastructure contract
Contract ID:
25OB0019
Fingerprint:
f3e3d6987d7ffd…5fcda50368 Verified
Status:
Terminated
Physical progress:
100%
Timeline:
Start Feb 17, 2025 (1 yr 8 mo ago) · Target/actual end Jul 1, 2026
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS CENTER) AT NATIONAL CENTER FOR MENTAL HEALTH, BARANGAY MAUWAY, MANDALUYONG CITY
Category:
GAA 2025 SSP
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contract amount:
₱13,161,987.05 (₱13.2M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OB0310Jun 20, 2025CONSTRUCTION (COMPLETION) OF SENATE PRESIDENT NEPTALI GONZALES GENERAL HOSPITAL AT BARANGAY MAUWAY PACKAGE 7, MANDALUYONG CITYCompleted₱94.5M
25OB0341May 20, 2025CONSTRUCTION OF MULTI LEVEL PURPOSE BUILDING, PACKAGE 2, BARANGAY DAANG BAKAL, MANDALUYONG CITYOn-Going₱19.4M
25OB0342May 20, 2025CONSTRUCTION OF MULTI LEVEL PURPOSE BUILDING, PACKAGE 2, BARANGAY HARAPIN ANG BUKAS, MANDALUYONG CITYCompleted₱19.4M
25OB0343May 20, 2025CONSTRUCTION OF MULTI PURPOSE BUILDING (BARANGAY HALL) ANNEX, BARANGAY ADDITION HILLS, MANDALUYONG CITYOn-Going₱29.1M
25OB0344May 20, 2025CONSTRUCTION OF MULTI PURPOSE BUILDING (NEAR ACTIVITY CENTER), NATIONAL CENTER FOR MENTAL HEALTH, MANDALUYONG CITYCompleted₱19.4M
25OB0348May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE INCLUDING UPRADING OF ELECTRICAL FACILITIES AT SANCTUARY DOH NCR PHASE 2, BARANGAY ADDITION HILLS, MANDALUYONG CITYCompleted₱14.6M
25OB0353May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY WACKWACK PACKAGE 7, MANDALUYONG CITYCompleted₱97.0M
25OB0354May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI LEVEL BUILDING AT ANDRES BONIFACIO INTEGRATED SCHOOL, MANDALUYONG CITYTerminated₱2.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.