Project 25OB0139
DPWH infrastructure contract
Contract ID:
25OB0139
Fingerprint:
0bffefe92198ce…3fa865ad0f Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Feb 18, 2025 (1 yr 8 mo ago)
Description:
CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LABASAN RIVER (WEST BANK), PHASE 1, PACKAGE 5, TAGUIG CITY
Category:
Flood Control and Drainage
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
TUCHAR CONSTRUCTION CORP. (FORMERLY:TUCHAR CONSTRU · DPWH contractor code 13644
Contract amount:
₱94,569,895.39 (₱94.6M)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OB0443 | Jul 13, 2026 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NEW LOWER BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱46.9M |
| 25OB0367 | Apr 15, 2026 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AND SITE DEVELOPMENT AT LAKESHORE AT BARANGAY LOWER BICUTAN, TAGUIG CITY | On-Going | ₱47.0M |
| 25OB0409 | Aug 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, NRCPO, CAMP BAGONG DIWA, TAGUIG CITY | On-Going | ₱29.1M |
| 25OB0437 | Aug 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SPD COMPOUND, LAWTON AVE., BARANGAY WESTERN BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱48.5M |
| 25OC0178 | Jul 8, 2025 | REHABILITATION/IMPROVEMENT OF SOUTH SUPER H-WAY WEST SERVICE RD (S03387LZ)(INTERMITTENT) PARAÑAQUE CITY, METRO MANILA | Completed | ₱12.8M |
| 25OB0371 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱48.5M |
| 25OB0372 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 2) | On-Going | ₱48.5M |
| 25OB0373 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 5) | On-Going | ₱72.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.