Project 25OB0152

DPWH infrastructure contract
Contract ID:
25OB0152
Fingerprint:
3e7a2791a26001…235dc23772 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 14, 2025 (1 yr 8 mo ago) · Target/actual end Jan 1, 2026
Description:
REHABILITATION OF ROAD AND DRAINAGE AT BLOCK 6,8 AND 9 AT BAGONG SIKAT ST., MASTRILI VILLE AND SAMATAG ST., ALL IN BARANGAY STA. ANA, TAGUIG CITY
Category:
GAA 2025 SSP
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
Contract amount:
₱32,584,681.75 (₱32.6M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OB0443Jul 13, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NEW LOWER BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱46.9M
25OB0367Apr 15, 2026CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AND SITE DEVELOPMENT AT LAKESHORE AT BARANGAY LOWER BICUTAN, TAGUIG CITYOn-Going₱47.0M
25OB0409Aug 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NRCPO, CAMP BAGONG DIWA, TAGUIG CITYOn-Going₱29.1M
25OB0437Aug 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, SPD COMPOUND, LAWTON AVE., BARANGAY WESTERN BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱48.5M
25OC0178Jul 8, 2025REHABILITATION/IMPROVEMENT OF SOUTH SUPER H-WAY WEST SERVICE RD (S03387LZ)(INTERMITTENT) PARAÑAQUE CITY, METRO MANILACompleted₱12.8M
25OB0371Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱48.5M
25OB0372Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 2)On-Going₱48.5M
25OB0373Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 5)On-Going₱72.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.