Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25OB0448

DPWH infrastructure contract
Contract ID:
25OB0448
Fingerprint:
cf0ff1ca1b3cd1…0c5e8d3a0b Verified
Status:
Terminated
Physical progress:
0%
Timeline:
Start May 20, 2025 (1 yr 5 mo ago) · Target/actual end Aug 5, 2025
Description:
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PUMPING STATION) AT BARANGAY BATIS, SAN JUAN CITY
Category:
GAA 2025 OO-2
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
Contract amount:
₱0.00 (₱0)
Funding source:
Regular Infra - GAA 2025 OO-2
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26OE0009Sep 2, 2026PREVENTIVE MAINTENANCE - TERTIARY ROADS - BAGUMBAYAN ST. - (S02401LZ) CHAINAGE 006 - CHAINAGE 170On-Going₱1.7M
25OB0103Feb 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SAN PERFECTO, SAN JUAN CITYOn-Going₱65.8M
25OE0130Feb 18, 2025REHABILITATION OF DRAINAGE ALONG BAGUMBAYAN ST., MANILA CITYCompleted₱20.2M
25OB0107Feb 17, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, KABAYANAN ELEMENTARY SCHOOL (SPED), BARANGAY KABAYANAN, SAN JUAN CITYOn-Going₱19.5M
25OE0133Feb 17, 2025REHABILITATION OF DRAINAGE ALONG P. SANCHEZ ST., MANILA CITYCompleted₱16.3M
25OB0095Feb 14, 2025ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - F MANALO - K0007 + (-894) - K0007 + (-240)Completed₱12.9M
25OB0097Feb 14, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (DAYCARE), BARANGAY BATIS, SAN JUAN CITYCompleted₱9.8M
25OB0100Feb 14, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, NICANOR IBUNA ELEMENTARY SCHOOL, SAN JUAN CITYOn-Going₱9.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.