Project 25OH0161

DPWH infrastructure contract
Contract ID:
25OH0161
Fingerprint:
edd8dd475ff712…575eccf738 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 15, 2025 (1 yr 6 mo ago) · Target/actual end Dec 10, 2025
Description:
IMPROVEMENT OF PASAY CITY - TOLENTINO ROTUNDA (DOMESTIC RD), PASAY CITY
Category:
GAA 2025 SSP
Implementing office:
DPWH South Manila DEO · National Capital Region
Contractor:
KPGONZALES CONSTRUCTION SUPPLY AND TRADING · DPWH contractor code 38822
Contract amount:
₱3,872,791.55 (₱3.9M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26OC0008Jul 29, 2026ASSET PRESERVATION PROGRAM-REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-ROXAS BLVD.-K0007+271-K0007+419, PARAÑAQUE CITY, METRO MANILAOn-Going₱7.0M
26OC0009Jul 29, 2026ASSET PRESERVATION PROGRAM-REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-ROXAS BLVD.-K0006+016-K0006+102, PARAÑAQUE CITY, METRO MANILAOn-Going₱1.6M
25O00098Jul 18, 2025CONSTRUCTION OF DPWH NCR REGIONAL OFFICE BUILDING, JW DIOKNO BLVD, PASAY CITY (PHASE IV)On-Going₱47.1M
25O00085May 8, 2025ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - IMPROVEMENT OF EPIFANIO DELOS SANTOS AVE (EDSA)-K0031+612 - K0032+284On-Going₱180.8M
25OH0109Apr 15, 2025INSTALLATION OF SOLAR LED STREETLIGHTS ALONG APELO CRUZ ST., PASAYOn-Going₱47.9M
25OH0112Apr 15, 2025INSTALLATION OF SOLAR LED STREETLIGHTS ALONG DOMESTIC ROAD, PASAYOn-Going₱95.9M
25OH0114Apr 15, 2025INSTALLATION OF SOLAR LED STREETLIGHTS ALONG ANDREW AVE, PASAYOn-Going₱47.9M
25OH0088Apr 11, 2025RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES-MALIBAY BR. NB ALONG EPIFANIO DELOS SANTOS AVE (EDSA)Completed₱95.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.