Project 26DL0056
DPWH infrastructure contract
Contract ID:
26DL0056
Fingerprint:
95424d36988c93…bf763de1b4 Verified
Status:
On-Going
Physical progress:
9.0%
Timeline:
Start Aug 4, 2026 (3 mos ago)
Description:
(TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP), LALAGUNA ECOTOURISM ROAD LEADING TO KAMPO PUSA, MARSHLAND, VERA SHRINE, CENTENNIAL TREES, COMMUNITY FLOWER GARDEN, AND COMMUNITY LIVELIHOOD CENTER AND DELICACIES, STA. 000+225 - STA. 000+380, LOPEZ, QUEZON
Category:
GAA 2026 CP
Implementing office:
DPWH Quezon 4th DEO · Region IV-A
Contractor:
DZEE BUILDERS & CONSTRUCTION SUPPLY · DPWH contractor code 36200
As listed: DZEE BUILDERS AND CONSTRUCTION SUPPLY
Contract amount:
₱3,410,714.90 (₱3.4M)
Funding source:
Regular Infra - GAA 2026 CP
Budget year:
2026
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26DL0058 | Aug 5, 2026 | NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, LOPEZ BYPASS ROAD - K0216 + 030 - K0216 + 323, K0218 + 076 - K0218 + 088, K0218 + 088 - K0218 + 166, K0218 + 166 - K0218 + 180, K0219 + 769 - K0219 + 860, K0220 + 000 - K0220 + 664 | On-Going | ₱24.4M |
| 25DL0198 | Jul 22, 2025 | BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS, CONSTRUCTION OF SCHOOL BUILDING, SAN RAFAEL ELEMENTARY SCHOOL, BARANGAY SAN RAFAEL, LOPEZ, QUEZON | Completed | ₱4.8M |
| 25DL0129 | Jun 18, 2025 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - SECONDARY ROADS, LOPEZ BYPASS RD - K0216+000 - K0217+000 | On-Going | ₱96.5M |
| 25DL0170 | May 27, 2025 | ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALO | On-Going | ₱9.5M |
| 25DL0171 | May 27, 2025 | ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TALOLONG RIVER, LOPEZ, QUEZON | On-Going | ₱93.1M |
| 25DL0175 | May 27, 2025 | ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL ALONG BOCBOC CREEK, LOPEZ, QUEZON | On-Going | ₱19.0M |
| 25DL0162 | May 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF VERGAÑA TO SAN ANDRES TO STA. CATALINA TO CAWA | Completed | ₱49.5M |
| 25DL0165 | May 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF BOCBOC CORE ROAD (LIPUTIHAN TO BRGY HALL TO BU | Completed | ₱24.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.