Project 26EI0127

DPWH infrastructure contract
Contract ID:
26EI0127
Fingerprint:
d23bb0624bf734…373c5ac596 Verified
Status:
On-Going
Physical progress:
25.0%
Timeline:
Start Jul 7, 2026 (4 mos ago)
Description:
ROAD WIDENING - SECONDARY ROADS - BONGABONG-SAGANA-ROXAS-SN AQUILINO RD-K0110+736 - K0111+334, K0115+078 - K0115+449, BONGABONG, ORIENTAL MINDORO
Category:
GAA 2026 OO-1
Implementing office:
DPWH Southern Mindoro DEO · MIMAROPA Region
Contractor:
BANAYAD CONSTRUCTION SERVICES · DPWH contractor code 51462
Contract amount:
₱25,997,591.69 (₱26.0M)
Funding source:
Regular Infra - GAA 2026 OO-1
Budget year:
2026

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26EI0063Jul 21, 2026ROAD WIDENING - SECONDARY ROADS - BONGABONG - SAGANA - ROXAS - SN AQUILINO RD - K0126+438 - K0126+539, K0126+635 - K0127+144, ROXAS, ORIENTAL MINDOROOn-Going₱17.4M
26EI0101Jul 21, 2026CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - CALAPAN SOUTH RD - K0138 + 928 - K0139 + 628, ROXAS, ORIENTAL MINDOROOn-Going₱16.6M
26EI0058Jul 7, 2026ROAD WIDENING - SECONDARY ROADS - CALAPAN SOUTH RD - K0137 + 483 - K0137 + 786, K0140 + 405 - K0141 + 213, ROXAS, ORIENTAL MINDOROOn-Going₱49.4M
25EI0100Jun 16, 2025CONSTRUCTION OF ROAD AT DIMATULAC ST., SITIO MALIGAYA, BRGY. SAN AQUILINO, ROXAS, ORIENTAL MINDOROCompleted₱4.9M
25EI0166Jun 16, 2025COMPLETION (CONSTRUCTION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. ODIONG, ROXAS, ORIENTAL MINDORO, PHASE IICompleted₱2.9M
25EI0046May 26, 2025IMPROVEMENT OF INTERSECTION AT CALAPAN SOUTH RD - K0140+000.00, BRGY. SAN AQUILINO, ROXAS, ORIENTAL MINDOROCompleted₱14.5M
25EI0178May 26, 2025RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES: HAGAN BRIDGE, HAGAN, BONGABONG, ORIENTAL MINDOROCompleted₱24.1M
25EI0148Apr 7, 2025SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-CONSTRUCTION OF ROAD AT DIMATULAC ST. SITIO MALIGAYA, SAN AQUILINO, ROXAS, ORIENTAL MINDOROCompleted₱4.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.