Project 26MI0046
DPWH infrastructure contract
Contract ID:
26MI0046
Fingerprint:
eaedc4cbead0db…f54ecf58cf Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 11, 2026 (5 mos ago) · Target/actual end Jul 30, 2026
Description:
RECONSTRUCTION OF DAMAGED PAVED ROADS ALONG MAKILALA-ALLAH VALLEY RD - K1644 + 050.00 - K1644 + 068, K1644 + 083 - K1644 + 204.50, K1644 + 237 - K1644 + 264, K1644 + 275 - K1644 + 279.50, K1644 + 280 - K1644 + 284.50, K1644 + 322 - K1644 + 331, K1644 + 34
Category:
GAA 2026 OO-1
Implementing office:
DPWH Cotabato 3rd DEO · Region XII
Contractor:
PADER CONSTRUCTION & SUPPLY · DPWH contractor code 20213
Contract amount:
₱3,940,212.69 (₱3.9M)
Funding source:
Regular Infra - GAA 2026 OO-1
Budget year:
2026
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26M00007 | Jun 10, 2026 | PREVENTIVE MAINTENANCE-MAKILALA-ALLAH VALLEY RD - K1639+000 - K1640+915, TULUNAN, NORTH COTABATO | On-Going | ₱143.0M |
| 25MI0098 | Aug 19, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET PHASE II) IN BARANGAY SIBSIB, TULUNAN, COTABATO | On-Going | ₱14.0M |
| 25MI0076 | Jul 28, 2025 | CONSTRUCTION OF ROAD FROM PUROK 4 TO PUROK 6 IN BRGY. NABUNDASAN, TULUNAN, COTABATO | Completed | ₱9.9M |
| 25MI0070 | Jun 27, 2025 | COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) FOR TUBURAN ELEMENTARY SCHOOL IN BRGY. TUBURAN, TULUNAN, COTABATO | Completed | ₱4.7M |
| 25MI0046 | May 23, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY PALMA PEREZ, MLANG, NORTH COTABATO | Completed | ₱4.9M |
| 25MI0064 | Mar 28, 2025 | REHABILIATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BAGUMBAYAN, TULUNAN, NORTH COTABATO | Completed | ₱4.7M |
| 25MI0061 | Mar 20, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY NEW PANAY, TULUNAN, NORTH COTABATO | Completed | ₱4.7M |
| 25MI0007 | Feb 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (DIGITAL LEARNING CENTER), BARANGAY POBLACION, TULUNAN, NORTH COTABATO | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.