Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 26MI0064

DPWH infrastructure contract
Contract ID:
26MI0064
Fingerprint:
3bb4b85ae4248e…0d5183077a Verified
Status:
On-Going
Physical progress:
89.1%
Timeline:
Start Jun 18, 2026 (4 mos ago)
Description:
ASPHALT OVERLAY ALONG MATALAM-MLANG-BAGONTAPAY JCT RD - K1644 + 133 - K1644 + 1025
Category:
GAA 2026 OO-1
Implementing office:
DPWH Cotabato 3rd DEO · Region XII
Contractor:
JARGON CONSTRUCTION & SUPPLY · DPWH contractor code 23474
Contract amount:
₱62,162,753.94 (₱62.2M)
Funding source:
Regular Infra - GAA 2026 OO-1
Budget year:
2026

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26MI0070Jul 15, 2026ROAD WIDENING ALONG BUKIDNON-COTABATO RD - K1654 + 923 - K1655 + 000Completed₱2.6M
26MI0063Jun 18, 2026ASPHALT OVERLAY ALONG DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT) - K1636 + 840 - K1637 + 706On-Going₱31.3M
26MI0066Jun 18, 2026ROAD WIDENING ALONG DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT) - K1636 + (-948) - K1636 + (-108)On-Going₱27.5M
26MI0048Jun 11, 2026ROAD WIDENING ALONG DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT) - K1638 + 000 - K1639 + 753On-Going₱47.5M
25MC0086Oct 29, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MALINAN, KIDAPAWAN CITY, NORTH COTABATOCompleted₱4.8M
25MI0099Aug 19, 2025CONSTRUCTION OF ROAD FROM NEW ABRA BRIDGE TO SITIO STO. NIÑO, BARANGAY NEW ABRA, MATALAM, NORTH COTABATOCompleted₱9.4M
25MI0079Jul 29, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DPWH-COTABATO 3RD DISTRICT ENGINEERING OFFICE, BRGY. MANUBUAN, MATALAM, COTABATOCompleted₱9.4M
25MI0083Jul 29, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY WEST PATADON, MATALAM, NORTH COTABATOCompleted₱4.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.